Large zinc and lead anomaly targeted at Yerelina
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
ASX : CXO
7th July 2015
Large zinc and lead anomaly
targeted by Core’s current exploration at Yerelina
HIGHLIGHTS
Zinc and lead anomalism identified in historic stream sediment survey
Coincident zinc and lead anomaly over 30km square kilometres in size
Core’s current exploration efforts focussed on this broad area of
anomalism and high grade surface mineralisation
Results expected over coming weeks
First drilling at Yerelina to commence this quarter
Core Exploration Ltd’s (ASX:CXO) soil surveys currently underway are targeting the source of zinc
and lead anomalism in stream sediments covering an area over 30 square kilometres in size at
Yerelina in South Australia.
A review of historic regional stream sediment sampling undertaken in the 1960’s highlights a
coincident zinc and lead anomaly at Yerelina including at the Great Gladstone and Big Hill prospects
(Figures 1 & 2). The elevated zinc and lead geochemical anomaly is defined within surface drainages
over an area in excess of 30 square kilometres.
Managing Director of Core Exploration, Stephen Biggins said “We are very excited by the results of
our latest analysis which have identified highly anomalous zinc and lead over an extremely large area
of 30 km2. The presence of old workings, a large area of highly anomalous zinc and lead and the
results of detailed magnetic surveys is potentially indicative of a substantial mineralising event.”
Core’s surface mapping, detailed magnetic surveys and remote sensing imagery also show clear
evidence of numerous historical workings and outcropping mineralisation that can be mapped over
hundreds to thousands of metres in repetitious gossanous vein sets within this 8km wide anomaly.
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Figure 1. Zinc in stream sampling image overlain by zinc rock chip assays, mineralised and interpreted structure, Yerelina SA.
Figure 2. Lead in stream sampling image overlain by zinc rock chip assays, mineralised and interpreted structure, Yerelina SA.
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Core has embarked on a soil sampling program targeting zinc and lead anomalism over the entire
area highlighted by the historic stream geochemical anomaly (Figures 1 & 2). Early reconnaissance
soil surveys by Core have already identified additional high grade mineralisation at surface at the
new Grace Prospect (ASX: 01/06/15).
Core’s Yerelina Zinc Project is highly prospective for shallow zinc mineralisation as evidenced by high
grade mineralisation identified to date on at least six separate north‐south structures identified by
Core and anomalous zinc and lead in stream sediments over this broad area (Figures 1 and 2).
Future Work Program
Further soil and rock results are anticipated during July as current field work progresses toward the
drilling of these zinc targets.
Core has also been recently awarded a grant as part of the SA Government’s PACE Discovery Drilling
2015 program. The proposed PACE assisted drilling project comprises a total of six angled diamond
core holes targeted under the known outcropping mineralisation.
Land access clearances have commenced to fast track the project for drilling as early as possible
during Q3 2015.
For further information please contact:
Stephen Biggins
Managing Director
Core Exploration Ltd
+61 8 7324 2987
info@coreexploration.com.au
The information in this report that relates to Exploration Results and Mineral Resources is based on information compiled
by Stephen Biggins (BSc(Hons)Geol, MBA) as Managing Director of Core Exploration Ltd who is a member of the
Australasian Institute of Mining and Metallurgy and is bound by and follows the Institute’s codes and recommended
practices. He has sufficient experience which is relevant to the styles of mineralisation and types of deposits under
consideration and to the activities being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the
“Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr. Biggins consents to the
inclusion in the report of the matters based on his information in the form and context in which it appears. This report also
references information previously released under JORC Code 2012 to the ASX on 02/06/15 titled “10m wide gossan found at
Yerelina Zinc Project”.
This report also includes exploration information that was prepared and first disclosed by Core under the JORC Code 2004. It
has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially
changed since it was last reported. The information in all previous announcements has been compiled by Mr Stephen
Biggins as the Competent Person and who provided his consent for all previous announcements. The information that was
reported in announcements previously released under JORC Code 2004 is the announcement dated 19/03/2013 titled “High
Grade Lead‐Zinc‐Silver Assays from S.A. Project”
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Yerelina – June 2015– JORC 2012
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
JORC Code explanation
Commentary
Sampling
techniques
Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
-80 mesh sieved stream sediment samples
Soil samples spacing varied on geological grounds
Data sourced from the SARIG geochemical database
Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
Aspects of the determination of mineralisation that are Material to the
Public Report.
Drilling
techniques
Drill sample
In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘RC drilling was used to obtain 1 m samples from
which 3 kg was pulverised to produce a 30 g charge for fire assay’).
In other cases more explanation may be required, such as where
there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (eg submarine nodules) may
warrant disclosure of detailed information.
Drill type (eg core, RC, open-hole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (eg core diameter, triple or standard
tube, depth of diamond tails, face-sampling bit or other type, whether
core is oriented and if so, by what method, etc).
Method of recording and assessing core and chip sample recoveries
Stream sediment sampling
Stream sediment sampling
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Criteria
JORC Code explanation
recovery
and results assessed.
Commentary
Measures taken to maximise sample recovery and ensure
representative nature of the samples.
Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
Logging
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
Stream sediment sampling
Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
Subsampling
techniques
and sample
preparation
The total length and percentage of the relevant intersections logged.
If core, whether cut or sawn and whether quarter, half or all core
taken.
If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
See Sampling section above for a description of sampling and subsampling techniques.
The nature, quality and appropriateness of the sampling technique is
considered adequate for the type of mineralisation and confidence
level being attributed to this sampling.
Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Criteria
JORC Code explanation
Commentary
duplicate/second-half sampling.
Quality of
assay data
and
laboratory
tests
Verification
of sampling
and
assaying
Whether sample sizes are appropriate to the grain size of the material
being sampled.
The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is considered
partial or total.
Analysis was undertaken by AAS circa 1966
For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including instrument
make and model, reading times, calibrations factors applied and their
derivation, etc.
Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels
of accuracy (ie lack of bias) and precision have been established.
The verification of significant intersections by either independent or
alternative company personnel.
Data sourced from SARIG database
Raw data sheets sited in historic reports
the use of twinned holes.
Documentation of primary data, data entry procedures, data verification,
data storage (physical and electronic) protocols.
Location of
data points
Discuss any adjustment to assay data.
Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations
used in Mineral Resource estimation.
Data and locations sourced from SARIG database
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Criteria
Data spacing
and
distribution
Orientation
of data in
relation to
geological
structure
Sample
security
Audits or
reviews
JORC Code explanation
Commentary
stream sediment sampling spacing varied on geological grounds
Specification of the grid system used.
Quality and adequacy of topographic control.
Data spacing for reporting of Exploration Results.
Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and classifications
applied.
Whether sample compositing has been applied.
Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering
the deposit type.
Reconnaissance stream sediment sampling only.
If the relationship between the drilling orientation and the orientation
of key mineralised structures is considered to have introduced a
sampling bias, this should be assessed and reported if material.
The measures taken to ensure sample security.
Circa 1966 data sourced from SARIG database
The results of any audits or reviews of sampling techniques and data.
No audits or reviews have been undertaken
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
JORC Code explanation
Commentary
Mineral
tenement
Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint
Yerelina is contained within EL 5015 that is 100% held by Sturt
Exploration Pty Ltd a wholly owned subsidiary of Core Exploration
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Criteria
JORC Code explanation
and land
tenure status
ventures, partnerships, overriding royalties, native title interests,
historical sites, wilderness or national park and environmental
settings.
The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
Core Exploration manages EL 5015.
Exploration
done by
other parties
Acknowledgment and appraisal of exploration by other parties.
All drilling was undertaken outside of Heritage, Conservation or
National Parks on EL 5015.
Modern exploration is very limited in the Yerelina area however
extensive historical workings dating back to 1908 are evident as a
number of shafts and drives
Geology
Deposit type, geological setting and style of mineralisation.
Drill hole
Information
A summary of all information material to the understanding of the
exploration results including a tabulation of the following information
for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
Data
aggregation
methods
Commentary
If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from
the understanding of the report, the Competent Person should clearly
explain why this is the case.
In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (eg cutting of high
grades) and cut-off grades are usually Material and should be stated.
Ltd.
EL 5015 is located on Mt Freeling Station.
The mineralisation style targeted is silver and base-metal veining
within an antiformal structure of Tapley Hill Formation
Initial reconnaissance stream sediment sampling only.
Initial reconnaissance stream sediment sampling only. No metal
equivalents are reported.
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Criteria
Relationship
between
mineralisatio
n widths and
intercept
lengths
Diagrams
Balanced
reporting
Other
substantive
exploration
data
Further work
JORC Code explanation
Commentary
Where aggregate intercepts incorporate short lengths of high grade
results and longer lengths of low grade results, the procedure used
for such aggregation should be stated and some typical examples of
such aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values
should be clearly stated.
These relationships are particularly important in the reporting of
Exploration Results.
If the geometry of the mineralisation with respect to the drill hole
angle is known, its nature should be reported.
If it is not known and only the down hole lengths are reported, there
should be a clear statement to this effect (eg ‘down hole length, true
width not known’).
Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported These should include, but not be limited to a plan view of
drill hole collar locations and appropriate sectional views.
Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be practiced to avoid misleading reporting of
Exploration Results.
Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical
survey results; geochemical survey results; bulk samples – size and
method of treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics; potential
deleterious or contaminating substances.
The nature and scale of planned further work (eg tests for lateral
extensions or depth extensions or large-scale step-out drilling).
Initial reconnaissance stream sediment sampling only.
See attached plans showing sample density.
All stream sediment samples in the area are represented in the
figures
Exploration activity is very limited at Yerelina however CXO collected
heli-magnetic and radiometric data in 2012, undertook previous rockchip sampling of anomalous gossans / historical mullock piles and
submitted a limited number of samples for petrology.
Subject to Board approval drilling may be undertaken
Diagrams clearly highlighting the areas of possible extensions,
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Criteria
JORC Code explanation
Commentary
including the main geological interpretations and future drilling areas,
provided this information is not commercially sensitive.
A 26 Gray Court, Adelaide SA 5000 | T (08) 7324 2987 | E info@coreexploration.com.au
www.coreexploration.com.au
Share your feedback
Discover