Quarterly Activities and Cashflow Report
Released
Released
Announcement PDF
Level 9, 2 Mill Street T 61 8 8317 1700 ABN 80 146 287 809
Perth WA 6000 E info@corelithium.com.au ASX CXO
corelithium.com.au
13 October 2025
ASX: CXO Announcement
September Quarterly Activities Report
Australian lithium company Core Lithium Ltd (ASX: CXO) (Core or Company) is pleased to provide its
quarterly activities report for the quarter ended 30 September 2025.
Summary
• Advancement of the Finniss Lithium Project (Finniss) towards restart as a highly attractive,
low-cost underground mining operation with a 20-year life1 based on the outcomes of the
Restart Study
• Firm commitments received for a two tranche $50 million (before costs) Placement and an
additional $4.3 million raised through a Share Purchase Plan (SPP) to accelerate the
development of Finniss
• Updated Ore Reserve for Carlton increases the total Finniss Ore Reserves by 42% to
15.2Mt at 1.26% Li2O2
• Strong interest received to date through the strategic funding process with engagement
from a range of high quality strategic investors and financial groups
• Termination of the final offtake agreement for Finniss leaves 100% of all future spodumene
production unencumbered and available for project partners or spot sales
• Cash balance of $35.9 million at 30 September 2025 (30 June 2025: $23.5 million), before
approval of the ~$20.8 million (before costs) Tranche 2 Placement, by Core shareholders
on 10 October 2025
Commenting on the September quarter 2025, Core CEO Paul Brown said:
“During the September quarter we built on the Restart Study, delivering a 42% uplift in Ore Reserves with the
inclusion of Carlton. FID-related technical workstreams and optimisation activities are progressing well, with
improvements to be reflected in subsequent disclosures. The $50 million Placement, together with the $4.3 million
SPP, has strengthened our balance sheet and enables us to accelerate critical early works. With all legacy offtake
obligations resolved, 100% of future Finniss production is unencumbered, providing maximum flexibility for the
strategic funding process. We are well-capitalised and focused on advancing Finniss towards restart and a Final
Investment Decision.”
1
Refer to ASX announcement "Restart Study Repositions Finniss Operations” on 14 May 2025. The range disclosed above is inclusive of relevant contingency.
2
Refer to ASX announcement “Updated Ore Reserve at Carlton” on 10 September 2025.
corelithium.com.au
2
Sustainability
No recordable injuries or environmental incidents were reported during the quarter. Care-and-maintenance
activities continued across multiple areas at Finniss. During the dry season, minor works were completed at BP33
and Grants, including targeted repairs around dam infrastructure and desilting of sediment basins. Water
management included the transfer of 166 ML from the Grants pit to surface storage.
Financial Position and Capital Management
Balance sheet
Core ended the quarter with $35.9 million cash at the bank (30 June 2025: $23.5 million), excluding the additional
$20.8 million (before costs) tranche two placement approved after the quarter ended (10 October 2025).
The higher cash balance quarter-on-quarter is driven by the proceeds of the capital raising initiated during the
Quarter, which is detailed in this Report below.
Cash outflows were in line with expectations, noting the following:
• The final payment for the crushing plant acquisition of $9.5 million
• One-off non-recurring payment of $3.0 million (US$2.0 million) in relation to the termination of the Ganfeng
offtake agreement (see below)
• Finniss site maintenance costs of $1.2 million, primarily related to DMS plant care and maintenance for
operational readiness, and site salaries
• Exploration expenditure of $0.5 million, primarily related to exploration salaries and tenement rents
• Expenses relating to employee and other corporate-related expenses of $3.9 million
Core has made strategic decisions that have contributed to the significant reduction in liabilities, strengthening its
financial position and enhancing the balance sheet with all offtake and onerous contracts from the operating period
at Finniss now resolved. All material exploration activities and initiatives related to the Final Investment Decision
(FID) are evaluated in the context of current funding and their relevance to advancing the Finniss project towards
FID.
Core continues to maintain a stockpile of approximately 5,000 tonnes of spodumene concentrate and 75,000
tonnes of lithium fines, which remain available for sale should market conditions improve.
Capital Raising
In late August 2025, the Company initiated a capital raising, whereby it received firm commitments to raise gross
proceeds of $50 million at a price of $0.105 per share through a two-tranche Placement (Placement) and follow
on SPP.
The Placement received strong support from new institutional investors, including a selection of high-quality
cornerstone investors from the Americas and Australia, led by Fourth Sail Capital LP, a privately held boutique
asset manager focused on investment opportunities in commodities.
The capital raising will enable Core to accelerate the advancement of FID and undertake operational readiness
activities, and strengthening Core’s balance sheet to support the ongoing strategic funding process.
The Placement was in two tranches as follows:
• Tranche 1: approximately 278.1 million New Shares were issued to raise ~$29.2 million (before costs)
using Core’s placement capacity under ASX Listing Rule 7.1. Issue of Tranche 1 shares occurred on 4
September 2025.
• Tranche 2: approximately 198.1 million New Shares raising ~$20.8 million (before costs), which was
approved at a meeting of shareholders held on 10 October 2025. Settlement of Tranche 2 will occur
shortly after the meeting date.
The SPP was conducted at an issue price of $0.105 per share, the same price as the Placement, to eligible
shareholders in Australia and New Zealand. The SPP raised ~$4.3 million through the issue of approximately 41.3
corelithium.com.au
3
million new CXO shares on 29 September 2025. The Company thanks participants in the Placement and for their
support.
Project and Strategic Funding Update
During the quarter, key technical workstreams including geotechnical, water management, mine design and
operational sequencing advanced materially and remain on schedule to support a Final Investment Decision. This
work continues to de-risk the restart plan and is aligned with the scope set out in the Restart Study. The strategic
funding process is progressing as planned, with strong interest from high-quality counterparties. Further updates
will be provided in the ordinary course.
Finniss Lithium Operations
Ore Reserve update
Following the release of the Finniss Restart Study (Restart Study) on 14 May 20253, the Company has continued
to evolve and further de-risk the operating plan for Finniss (Figure 1). By leveraging the substantial body of study
work that has been completed, an Ore Reserve Estimate (ORE) was declared at Carlton to add to the existing
ORE for the Grants and BP33 deposits.
The Carlton ORE and related assumptions were developed and supported by independent consultants in
conjunction with Core’s Competent Persons. Supporting information and a JORC Table 1 can be found in the ASX
announcement “Updated Ore Reserve at Carlton” released on 10 September 2025.
Figure 1 Location of the Finniss Operation, including key deposits and infrastructure
3
Refer to ASX announcement “Restart Study Repositions Finniss Operations” on 14 May 2025.
corelithium.com.au
4
There has been no change to the Mineral Resource Estimate (MRE) for the Finniss Project, which includes the
Carlton deposit. The Finniss Project MRE is presented in Table 1.
Table 1 Finniss Project Mineral Resources Estimates
Mineral Resource Estimate for the Finniss Lithium Project
Mineral Resource Measured Indicated Inferred Total
Tonnes Li2O Tonnes Li2O Tonnes Li2O Tonnes Li2O Li2O
(Mt) % (Mt) % (Mt) % (Mt) %
Contained
Metal (kt)
Grants 1.34 1.48 0.61 1.49 0.37 1.27 2.32 1.45 33.6
BP33 2.85 1.44 6.51 1.55 1.14 1.59 10.5 1.53 161
Carlton 2.14 1.33 3.43 1.32 0.78 1.14 6.34 1.3 82.6
Lees - - 4.16 1.18 7.08 1.12 11.2 1.14 128
Ah Hoy - - 1.71 1.2 2.93 1.38 4.64 1.31 60.8
Booths - - 1.84 0.99 1.4 1.06 3.24 1.02 33
Penfolds - - 0.65 1.25 0.71 1.24 1.36 1.24 16.9
Hang Gong - - 1.51 1.18 1.95 1.14 3.46 1.16 40.1
Sandras - - 1.17 0.92 0.57 0.82 1.73 0.89 15.4
Bilatos - - - - 1.92 1.03 1.92 1.03 19.8
Seadog - - - - 1.41 1.18 1.41 1.18 16.6
Total 6.33 1.41 21.6 1.30 20.3 1.18 48.2 1.26 608
TSF/Rejects - - 0.31 0.66 - - 0.31 0.66 2.0
Total 6.33 1.41 21.9 1.29 20.3 1.18 48.5 1.26 610
1. Totals within this table are subject to rounding.
2. There was no cut-off applied to the TSF/Rejects material.
Mineral Resources from Carlton were previously included in the Mining Schedule of the Restart Study. Measured
and Indicated Resources were included from Year 9 to 20 of the proposed mine life, while Inferred Resources
were included from Year 13 to 204. As of this announcement, 81% of Measured and Indicated Resources from
Carlton have been converted to Ore Reserves.
Ore Reserves
The overall Project Ore Reserve Estimate has increased by 42.0% to 15.2Mt @ 1.26% with a 38.7% increase in
contained metal to 192kt Li2O5.
Proved and Probable Ore Reserves were estimated for Carlton. Measured Mineral Resources were converted to
Proved Ore Reserves, and Indicated Mineral Resources were converted to Probable Ore Reserves with the
application of modifying factors. No Probable Ore Reserves have been derived from Measured Mineral
Resources. The criteria used for the classification of the MRE on which the ORE is based is as follows:
• drilling data spacing, grade and geological continuity, and data integrity.
• the relative contributions of geological and data quality and confidence, as well as grade confidence and
continuity.
• confidence in the Measured and Indicated mineral resource is sufficient to allow application of modifying
factors within a technical and economic study.
The confidence level of the assumptions used is at a Pre-Feasibility level. The effective date of the Carlton ORE
is 5 September 2025.
4
Refer to ASX announcement “Restart Study Repositions Finniss Operations” on 14 May 2025.
5
Refer to ASX announcement “Updated Ore Reserve at Carlton” on 10 September 2025.
corelithium.com.au
5
Table 2 Finniss Ore Reserve Estimate, including contained metal
Deposit Category Ore Tonnes (Mt) Li2O (%) Contained Li2O kt
BP33
Proved 2.6 1.27 32
Probable 6.7 1.32 89
Total 9.3 1.31 121
Grants
Proved 0.9 1.29 11
Probable 0.3 1.36 4
Total 1.2 1.31 15
Carlton
Proved 1.7 1.19 20
Probable 2.8 1.19 34
Total 4.5 1.19 53
TSF/Stockpiles
Probable 0.3 0.68 2
Total 0.3 0.68 2
Total
Proved 5.1 1.25 63
Probable 10.1 1.27 128
Total 15.2 1.26 192
1. Effective date of the Ore Reserves is 5 September 2025.
2. Effective date of the Grants, BP33 and TSF/Stockpiles Ore Reserves is 30 April 2025.
3. Ore Reserves are the total for the Grants, BP33, TSF/Stockpiles and Carlton Mines.
4. The long-term SC6 Spodumene price used for calculating the financial analysis is US$1,330/t. The financial analysis has been estimated
with assumptions for crushing, processing and treatment charges, deductions and payment terms, concentrate transport, metallurgical
recoveries, and royalties.
5. The breakeven cut-off net Smelter Return (NSR) for underground mining at BP33 and Grants Underground is $110/t NSR and $125/t
NSR for Carlton Underground.
6. Measured Mineral Resources were used to estimate Proved Ore Reserves; Indicated Mineral Resources were used to estimate
Probable Ore Reserves.
7. Tonnage and grade estimates include dilution and recovery allowances.
8. The tonnage and grade for TSF/Stockpile are estimated from the operations reconciled monthly production records.
9. The Reserves are defined at the point where the ore is delivered to the processing plant.
10. The Ore Reserves reported above are not additive to the Mineral Resources.
11. Totals within this table are subject to rounding.
Exploration Target
Core has defined an Exploration Target of between 1.2 and 1.8Mt at a grade of 1.2 and 1.4% Li2O below the
existing Carlton Mineral Resource (ML31726)6.
Cautionary Statement related to the Carlton, BP33 and Blackbeard Exploration Targets: The potential
quantity and grade of the Exploration Targets is conceptual in nature. There has been insufficient
exploration to estimate a Mineral Resource, and it is uncertain if further exploration will result in the
estimation of a Mineral Resource.
The new Exploration Target is in addition to the Mineral Resource Estimate of 48.5Mt @ 1.26% Li2O already
defined by Core at Finniss and is summarised in Table 3.
6
Refer to ASX announcement “Updated Ore Reserve at Carlton” on 10 September 2025
corelithium.com.au
6
Table 3 Carlton Exploration Target
Exploration Target Tonnage (Mt) Li2O (%)
Low High Low High
Carlton 1.2 1.8 1.2 1.4
Drilling is planned to test the Carlton Exploration Target. Due to cost efficiencies and the planned underground
mining method, drilling to test the Exploration Target area will be undertaken from underground drilling positions
as part of future mining operations, rather than surface drilling. The timing of undertaking the planned 2,000m of
drilling required to test the Exploration Target is contingent upon the commencement of mining operations.
The Carlton Exploration Target is in addition to the combined BP33 and Blackbeard Exploration Target of 10.9Mt
– 16.5Mt at a grade of between 1.5% and 1.7% Li2O7.
Exploration
Lithium Exploration
At Blackbeard, planning for a diamond drilling program in FY26 remains ongoing. This program is designed to
test the geology and lithium mineralisation associated with the Exploration Target at depth. The objective is to
gather sufficient geological data to assess the potential for a future Mineral Resource Estimate.
Gold Exploration
The Mt Shoobridge prospect, part of Core’s wholly owned Shoobridge Gold Project, is strategically located
approximately 10km from the Stuart Highway and 60km from the Union Reefs gold processing plant, within the
Pine Creek Orogen – a region that hosts multiple multi-million-ounce gold deposits. With gold prices trading
around record highs, Shoobridge presents a strategic opportunity alongside Core’s primary focus on lithium.
Drilling and surface geochemical sampling were conducted during the quarter at Mt Shoobridge.
Corporate
Settlement of Ganfeng Offtake Agreement
During the quarter, Core made a one-off payment of $3.0 million (US$2.0 million) in cash to terminate the existing
offtake agreement with Ganfeng Lithium Co. (Ganfeng) in relation to the sale of spodumene concentrate.8
All spodumene offtake obligations for Finniss have now been removed, leaving 100% of future Finniss production
unencumbered. This provides Core with complete marketing flexibility, with all future spodumene concentrate
production now available for project partners or spot sales. It also delivers increased optionality within the current
strategic funding process for Finniss, enhancing the Company’s ability to partner with additional new
counterparties.
7
Refer to ASX announcement “Updated Finniss Lithium Project Reserve and Resource” on 14 May 2025
8
Refer to ASX announcement “Termination of Final Offtake Agreement for Finniss” on 25 September 2025.
corelithium.com.au
7
Other disclosures
As at 30 June 2025, Core had the following capital structure:
• 2,462,390,658 ordinary shares
• 17,034,852 unquoted performance rights
• 7,500,000 unquoted options
Core’s Appendix 5B includes an amount of $94k in item 6.1. The amount in item 6.1 represents director fees paid
to entities nominated by the Company’s directors.
Core confirms that it is not aware of any new information or data that materially affects the exploration results,
exploration targets, MRE and ORE included in this announcement as cross referenced in the body of this
announcement, and that all technical parameters and material assumptions underpinning the MRE, ORE and
production target and forecast financial information derived from the production target continue to apply and have
not materially changed except as reported within this release. The Company confirms that the form and context
in which the Competent Person’s findings are presented have not been materially modified from the original
announcements related to previously reported exploration results, exploration targets, MRE and ORE.
corelithium.com.au
8
Tenements
Tenement number Tenement name Interest at the end
of Quarter
Changes during
the Quarter
South Australia
EL 6574 Fitton 100% None
EL 6038 Mt Freeling 100% None
EL 6111 Yerelina 100% None
EL 6445 Wyatt Bore 100% None
Northern Territory
EL 26848 Walanbanba 100% None
EL 28029 White Range East 100% None
EL 28136 Blueys 100% None
EL 29347 Yambla 100% None
EL 29389 Mt George 100% None
EL 29580 Jervois East 100% None
EL 29581 Jervois West 100% None
EL 29698 Finniss 100% None
EL 29699 Bynoe 100% None
EL 30012 Bynoe 100% None
EL 30015 Bynoe 100% None
EL 30793 McLeish 100% None
EL 31058 Barrow Creek 100% None
EL 31126 Zola 100% None
EL 31127 Ringwood 100% None
EL 31139 Anningie West 100% None
EL 31140 Anningie South 100% None
EL 31145 Barrow Creek North 100% None
EL 31146 Barrow Creek South 100% None
EL 31271 Bynoe 100% None
EL 31279 Sand Palms 100% None
EL 31407 Shoobridge 100% None
EL 31449 Napperby 100% None
EL 31886 Adelaide River 100% None
EL 32205 Finniss Range 100% None
EL 32392 Ivy 100% None
EL 32396 Murray Creek 100% None
EL 33932 Bloodwood 100% None
EL 33933 West Dam 100% None
.
corelithium.com.au
9
Tenements(cont.)
Tenement number Tenement name Interest at the end
of Quarter
Changes during
The Quarter
Northern Territory
EMP 28651 Observation Hill (Extractive Lease) 100% None
ML 29912 Saffums 100% None
ML 29914 Labelle 100% None
ML 29985 Angers North 100% None
ML 31654 Annie/Old Crusher 100% None
ML 31726 Grants Mineral Lease 100% None
ML 32074 Observation Hill (Ancillary Lease) 100% None
ML 32278 Grants Dam (Ancillary Lease) 100% None
ML 32346 BP33 Mineral Lease 100% None
MLN16 Bynoe 100% None
MLN813 Bilatos 100% None
MLN1148 Centurian 100% None
This announcement has been approved for release by the Core Lithium Board:
For further information, please contact:
Investor Enquiries
Paul Brown
CEO
Core Lithium Ltd
+61 8 8317 1700
info@corelithium.com.au
Media enquiries
Michael Vaughan
Executive Director
Fivemark Partners
+61 422 602 720
michael.vaughan@fivemark.com.au
About Core
Core Lithium Ltd (ASX: CXO) (Core or Company) is an Australian hard-rock lithium company that owns the
Finniss Lithium Operation on the Cox Peninsula, south-west and 88km by sealed road from the Darwin Port,
Northern Territory. Core's vision is to generate sustained value for shareholders from critical minerals exploration
and mining projects underpinned by strong environmental, safety and social standards.
For further information about Core and its projects, visit www.corelithium.com.au
Important Information
This announcement may reference forecasts, estimates, assumptions, and other forward-looking statements.
Although the Company believes that its expectations, estimates and forecast outcomes are based on reasonable
assumptions, it cannot assure that they will be achieved. They may be affected by various variables and changes
in underlying assumptions subject to risk factors associated with the nature of the business, which could cause
results to differ materially from those expressed in this announcement. The Company cautions against reliance
on any forward-looking statements in this announcement.
corelithium.com.au
10
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Core Lithium Ltd
ABN
Quarter ended (“current quarter”)
80 146 287 809 30 September 2025
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(3 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for - -
exploration & evaluation
development - -
production - -
staff costs (2,957) (2,957)
administration and corporate costs (954) (954)
care and maintenance (1,242) (1,242)
technical study costs (571) (571)
1.3 Dividends received (see note 3) - -
1.4 Interest received 204 204
1.5 Interest and other costs of finance paid (655) (655)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other – crushing contract payment (3,230) (3,230)
Other – offtake agreement payment (3,045) (3,045)
1.9 Net cash from / (used in) operating
activities
(12,450) (12,450)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
entities
tenements - -
property, plant and equipment (6,271) (6,271)
exploration & evaluation (543) (543)
investments - -
other non-current assets - mine
development
- -
2.2 Proceeds from the disposal of: - -
entities
tenements - -
property, plant and equipment - -
investments - -
other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
corelithium.com.au
11
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(3 months)
$A’000
2.5 Other (Net proceeds / (payments) for
Security bond)
- -
2.5a Other (Government grant co-funding (paid)) - -
2.5b Other (Government grant co-funding
received)
- -
2.6 Net cash from / (used in) investing
activities
(6,814) (6,814)
3. Cash flows from financing activities
33,528 33,528
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(1,693) (1,693)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (Payments of lease liabilities) (135) (135)
3.10 Net cash from / (used in) financing
activities
31,700 31,700
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
23,486 23,486
4.2 Net cash from / (used in) operating activities
(item 1.9 above)
(12,450) (12,450)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(6,814) (6,814)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
31,700 31,700
4.5 Effect of movement in exchange rates on
cash held
1 1
4.6 Cash and cash equivalents at end of
period
35,923 35,923
corelithium.com.au
12
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 35,923 23,486
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
35,923 23,486
6. Payments to related parties of the entity and their associates Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
94
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a
description of, and an explanation for, such payments.
7. Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the
entity.
Add notes as necessary for an
understanding of the sources of finance
available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing facilities
have been entered into or are proposed to be entered into after quarter end, include a note
providing details of those facilities as well.
N/A
corelithium.com.au
13
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (12,450)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(543)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (12,993)
8.4 Cash and cash equivalents at quarter end (item 4.6) 35,923
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 35,923
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
2.8
Note: if the entity has reported positive relevant outgoings (i.e. a net cash inflow) in item 8.3,
answer item 8.7 as “N/A”. Otherwise, a figure for the estimated quarters of funding available
must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above
must be answered.
corelithium.com.au
14
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which comply with
Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: 13 October 2025
Authorised by: By the Board
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market
about the entity’s activities for the past quarter, how they have been financed and the effect this has had
on its cash position. An entity that wishes to disclose additional information over and above the minimum
required under the Listing Rules is encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards,
the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and
AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report has been prepared
in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the
corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from
investing activities, depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here:
“By the board”. If it has been authorised for release to the market by a committee of your board of directors,
you can insert here: “By the [name of board committee – e.g. Audit and Risk Committee]”. If it has been
authorised for release to the market by a disclosure committee, you can insert here: “By the Disclosure
Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold
yourself out as complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate
Governance Principles and Recommendations, the board should have received a declaration from its CEO
and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this
report complies with the appropriate accounting standards and gives a true and fair view of the cash flows
of the entity, and that their opinion has been formed on the basis of a sound system of risk management
and internal control which is operating effectively.