June Quarterly Activities Report
Core Lithium Ltd (ASX: CXO) (Core or Company) is pleased to provide its quarterly activities report for
the quarter ended 30 June 2026 (Quarter).
Highlights
• Core continued to advance the Finniss Lithium Operation (Finniss) during the June quarter,
with key development and operational milestones delivered.
• Open pit mining rapidly commenced at Grants open pit following the award of the surface
mining contract to NRW Pty Ltd1. First shipment of newly produced product remains on
track for the December quarter.
• Underground decline development commenced at BP33, with the portal cut completed in
June following the award of the underground mining contract to Develop Global Ltd2.
• Executed agreements with Glencore International AG for the total sale of ~45kt of lithium
fines from the existing Finniss stockpile3, providing near term cash generation.
• Logistics chain commissioned and fully operational, with first product shipment of stockpiled
lithium fines and spodumene concentrate completed through Darwin Port.
• Commenced an offtake process to assess proposals and strategic options regarding
offtake, exploring ways to leverage an unencumbered offtake position.
• Blackbeard exploration program commenced targeting a maiden Mineral Resource
Estimate with 12,150 metres planned.
• Strengthened the Finniss tenement package through the agreement to acquire the Bynoe
Lithium tenement from Charger Metals (EL 30897)4.
• Strong funding position following completion of Tranche 2 of the A$120 million equity
raising, securing ~A$67 million (before costs)5; and receipt of Tranche 1 of the US$26
million (~A$37 million) Convertible Note funding6 and proceeds from Lithium fines sales.
• Cash balance of A$181.8 million at 30 June 2026 (31 March 2026: A$91.6 million).
1 Refer to ASX announcement “Grants Open Pit Mining to Commence” on 7 April 2026.
2 Refer to ASX announcement “Core Awards BP33 Underground Mining Contract at Finniss” on 13 May 2026.
3 Refer to ASX announcement “Sale of 20,000 tonnes of Lithium Fines” on 30 April 2026 and “Second Sale of Lithium Fines” on 10 June 2026.
4 Refer to ASX announcement “Finniss Exploration Program Commenced and Bynoe Tenement Acquired” on 19 June 2026.
5 Refer to ASX announcement “Completion of Tranche 2 of Finniss Equity Funding” on 8 May 2026.
6 Refer to ASX announcement “Receipt of Tranche 1 Convertible Note Funds” on 10 April 2026.
corelithium.com.au
2
Commenting on the June quarter 2026, Core Managing Director Paul Brown said:
“The June quarter was a defining period for Core, characterised by disciplined project execution and meaningful
operational progress. In just a few months, we have transitioned rapidly into execution mode, recommencing open
pit mining at Grants, commencing underground development at BP33, launching our exploration program,
strengthening our tenement package, activating our logistics chain and completing two sales from our fines
stockpiles generating cash from material already on site and further strengthening our liquidity position.
“We have also taken steps to sharpen our strategic focus with plans to divest our gold and non-lithium exploration
assets into Axiant Resources Limited, a proposed new IPO where Core will retain a significant holding. This will
allow us to focus our capital and efforts fully on building Finniss into a long-life lithium operation.
“I would also like to take this opportunity to again express my gratitude to Greg English, who has retired as Chair
and will be the new Chair of Axiant, for his significant contribution to Core over many years. Under Greg’s
leadership, Core has grown from a micro-cap South Australian exploration company into Australia's newest lithium
producer. We welcome Malcolm McComas as our Chair and look forward to his guidance as we enter this exciting
next phase.
“Core is in a very strong operational and financial position, with the foundations in place to continue executing to
plan and ample funding to advance Finniss to steady state production in 2028. We continue to execute against
our plans, delivering key milestones safely, on time and within budget. With strong momentum across the project,
we are focused on execution and look forward to delivering the first newly produced spodumene concentrate in
the December quarter.”
Finniss Lithium Operation
Grants
Mining Operations Commenced
During the quarter, open pit mining operations commenced at Grants open pit (Grants), including drill and blasting
activities and excavation work, representing a key milestone in the delivery of the Finniss restart and signalling
the transition toward near-term production and cash flow generation.
The commencement of mining follows the award in April 2026 of the surface mining services contract to NRW Pty
Ltd for open pit mining at Grants. The scope of work under the ~A$50 million contract includes all key activities
related to the delivery of material to the Grants Run of Mine (ROM) pad7.
Grants is a key component of the Finniss execution plan, providing near-term ore feed for the processing plant,
enabling an accelerated production timeline at a lower initial capital cost.
The optimised Grants pit design provides access to approximately 784kt of ore and is expected to deliver
approximately 134kt of SC5 product in total8. Ore from Grants is expected to be processed during the September
quarter, with the first spodumene concentrate shipment targeted in the December quarter, followed by further
shipments into CY2027.
Plant upgrades completed in the Quarter included removal, refurbishment and reinstallation of secondary fines
separation screens, relocation of ferrosilicon distribution pumping and piping system and the consolidation of
crusher and DMS plant into a single control room.
In addition, key engineering milestones for brownfields work are on track with packages scheduled for installation.
Recruiting and onboarding of the processing team, including operators, trades personnel and metallurgical staff
is tracking to plan.
7 Refer to ASX announcement “Grants Open Pit Mining to Commence” on 7 April 2026.
8 Refer to ASX announcement “FID Approved and Funding Secured for Finniss Restart” on 18 March 2026.
corelithium.com.au
3
Figure 1 Grants open pit operations (clockwise from top left) 1. Grants open pit April 2026 2. First blast at Grants
May 2026 3. Grants open pit June 2026 4. Plant upgrades underway with secondary DMS screen lifted out for
refurbishment upgrade
BP33
Several construction and underground development milestones were completed at BP33 during the Quarter.
Construction
Key construction activities during the Quarter at BP33 included:
• Mobilisation of civil contractor for bulk earthworks and the contractor for mine water dam construction
• Box cut successfully dewatered, construction of temporary box cut sump and cutback of box cut walls
completed
• Remediation of box cut and installation of ground support in the box cut portal location including shotcrete,
self drilling anchors, mine mesh, depressurisation holes and bench drains
• Completion of earthworks pads for paste plant, ventilation rises and power plant
• Completion of earthworks on portions of the mine water dam and commencement of geofabric and liner
installation
• Completion of the underground contractor laydown pad
In advance of the underground development commencing, Core commenced preliminary works at BP33 with box
cut rehabilitation and infrastructure site works progressing on schedule. Bulk earthworks for the non-process
infrastructure continue to progress, with the pads for the power station and ventilation system complete.
corelithium.com.au
4
Underground Development
For the underground development, key activities during the Quarter at BP33 included:
• Major contract for underground decline development awarded
• Mobilisation of the underground contractor commenced with mobile fleet delivered and commissioned
including jumbo, underground loader, roadheader, shotcrete machine, agitator trucks, and integrated tool
carrier
• Handover of laydown pad and box cut to underground contractor
• Establishment of temporary mine services to box cut
• Portal cut and underground development commenced
In May, Core awarded a three year contract valued at ~A$274 million to Dev Mining Services Pty Ltd, a subsidiary
of Develop Global Limited (ASX: DVP) (Develop), for underground mining services at the BP33 deposit.9
Following the award, Develop mobilised efficiently to site and underground decline development activities
commenced on schedule.
The establishment of the portal and start of underground decline development represent an important operational
milestone for Core. It reflects continued progress of the Company’s staged operations ramp up, marking the early
phase of Finniss’ transition from initial open pit operations at Grants to a long-life underground mining operation
commencing with BP33. The development remains on schedule with first development ore from BP33 expected
in mid-2027, with steady state production targeted for mid-2028.
Figure 2 BP33 underground decline progress
9 Refer to ASX announcement “Core Awards BP33 Underground Mining Contract at Finniss” on 13 May 2026.
corelithium.com.au
5
Figure 3 BP33 box cut
Figure 4 BP33 portal cut progress
corelithium.com.au
6
Figure 5 BP33 site overview
Logistics Chain
The Finniss logistics chain is now fully operational, marked by the successful departure of a shipment of 20kt
lithium fines10 and 5kt of stockpiled spodumene concentrate11 exported via Darwin Port, with payment received in
the Quarter. The shipment represents the successful remobilisation of Core’s established mine-to-port logistics
network, building on the operational and development progress made at Finniss.
Figure 6: Product shipment via Darwin Port
10 Refer to ASX announcement “Sale of 20,000 tonnes of lithium fines” on 30 April 2026 for further information.
11 Refer to ASX announcement “Sale of spodumene concentrate stockpile” on 26 February 2026 for further information.
corelithium.com.au
7
Exploration
Blackbeard Exploration Program Commenced
During the Quarter, Core commenced its 2026 exploration program at Finniss. The exploration program is
designed to support Core’s broader strategy of resource growth and mine life extension at Finniss, as well as
advancing the development pipeline. The primary objective is advancing the Blackbeard prospect toward a
maiden Mineral Resource Estimate (MRE).
Core has defined an Exploration Target of 7.0 to 10.0Mt at a grade of 1.5% to 1.7% Li2O12 for the highly
prospective Blackbeard prospect, with the target defined by ten existing RC holes drilled by Core. The best
previous intersection of 63m @ 1.67% Li2O in NRC26913 provides encouragement that a large mineralised system
may be present. The Blackbeard exploration program is a staged and gated diamond-drilling campaign totalling
12,150m in 2026 and forms part of Core’s strategy to expand and optimise operations at Finniss. Drilling has
commenced and is expected to be completed during the September quarter, with assay results to be released
progressively as received and validated.
The Exploration Target is supported by historical drilling, trenching and exploration results. The potential quantity
and grade of the Exploration Target is conceptual in nature. There has been insufficient exploration to estimate a
Mineral Resource and it is uncertain if further exploration will result in the estimation of a Mineral Resource.
Bynoe Lithium Tenement
Core entered into a binding agreement with Charger Metals NL (Charger) to acquire 100% of Charger’s interest
in the Bynoe Lithium Tenement (Bynoe), for initial consideration of A$3.75 million14. Bynoe comprises the EL
30897 tenement area. EL 30897 covers approximately 63km2 of land within the Finniss tenement area, which in
turn surrounds Core’s Blackbeard prospect. The acquisition is conditional on gaining the necessary statutory and
regulatory approvals and includes a deferred cash payment of A$1.0 million on a Mineral Resource Estimate, and
a 1% gross revenue royalty capped at A$10 million.
The agreement to acquire Bynoe consolidates Core’s tenement holdings within Finniss and enhances the
Company’s future exploration pipeline.
Figure 7: Overview of Finniss showing Blackbeard location relative to Core’s existing processing plant, and the
consolidation of the Bynoe tenement (EL 30897)
12 Refer to ASX announcement "Updated Finniss Lithium Project Ore Reserve and Mineral Resource Estimate” on 14 May 2025 for further information.
13 Refer to ASX announcement “New High-grade Lithium Drill Results within 20km of Grants” on 6 November 2024 for further information.
14 Refer to ASX announcement “Exploration Program Commenced and Bynoe Tenement Acquired” on 19 Junel 2026 for further information.
corelithium.com.au
8
Sustainability
There were no recordable injuries, significant safety or environmental incidents reported during the Quarter.
Emergency Services Officers have been deployed to support all work fronts across Grants and BP33 with Incident
Management Protocol re-established across both sites.
Water and land management remained a primary focus. Routine inspections, water quality monitoring and
sampling continued across Grants and BP33, with daily and weekly programs maintained and harbour sampling
completed.
Grants pit dewatering activities were completed during the Quarter. At BP33, discharge infrastructure remained
fully operational throughout the Quarter allowing the box cut to be prepared for the commencement of the
underground decline development.
Corporate
Funding package
During the Quarter, Core received proceeds from Tranche 1 of the Convertible Note funding, as part of the
Strategic Funding Package (Funding Package) announced on 18 March 202615, for proceeds of US$26 million
(~A$37 million).
At the General Meeting held on 5 May 2026 (Meeting), Core shareholders approved Tranche 2 of the Convertible
Notes, representing the deferred US$44 million component of the US$70 million of Convertible Notes issued to
Glencore International AG (Glencore) and InfraVia Capital Partners (InfraVia). The final completion of the
Convertible Notes remains subject to Foreign Investment Review Board (FIRB) approval.
At the Meeting, Core shareholders also approved Tranche 2 of its A$120 million equity raising, securing
approximately A$67 million (before costs) upon its completion16.
The overall Funding Package supports mining activities for Finniss and comprises a US$70 million Convertible Note
investment, a US$50 million senior secured debt facility, and a A$120 million equity raising17.
Financial Position and Capital Management
Core ended the Quarter with A$181.8 million cash at bank (31 March 2026: A$91.6 million).
Cash flows were in line with expectations, noting the following:
• A$67.3 million (before costs) was received following the settlement of Tranche 2 of the equity raising
following approval by Core shareholders at the Meeting.
• A$37.0 million (before costs) was received following the Tranche 1 of the Convertible Notes issued to
InfraVia.
• Proceeds of A$16.2 million from the sale of the Finniss spodumene concentrate stockpile and the first
sale of 20,000 tonnes (t) of lithium fines
• Finniss site capital works of A$15.5 million, primarily related to Grants reestablishment, DMS plant works
and BP33 works and supporting surface infrastructure.
• Exploration expenditure of A$0.4 million, primarily related to exploration salaries and tenement rents.
• Expenses relating to employee and other corporate-related expenses of A$10.7 million.
15 Refer to ASX announcement “Notice of 2026 Shareholder Meeting and Proxy Form” on 2 April 2026.
16 Based on exchange rate of AUD/USD $0.7074.
17 Refer to ASX announcement “FID Approved and Funding Secured for Finniss Restart” on 18 March 2026.
corelithium.com.au
9
Sales of Lithium Fines
During the Quarter, Core entered into two binding agreements with Glencore for the sale of its lithium fines
(lithium fines) from Finniss. The first sale, in April, was for 20,000 tonnes (t) of lithium fines at a base price of
US$290/t (A$405/t) CIF. The second, in June, was for 25,000 tonnes (t) of lithium fines from Finniss at a base
price of US$270/t (~A$375/t) CIF18.
The sales represent a further step in Core’s strategy to monetise existing stockpiled material and generate cash
flow while mining, processing and development activities at Finniss progress, with A$16.2 million cash received
from the first fines and concentrate shipment in the June Quarter.
These transactions demonstrate the value of Core’s existing Finniss logistics chain and its strategic partnership
with Glencore. The Company continues to explore pathways for the sale of the remaining ~30kt fines stockpile.
Offtake Process
Core has commenced an offtake process to assess proposals and strategic options regarding offtake, to explore
ways to leverage an unencumbered offtake position.
The commencement of the offtake process highlights Core’s flexibility to place offtake within its purchase and
distribution arrangement with Glencore for the sale of lithium products from Finniss19. The 5-year marketing
agreement includes flexible arrangements for shipping, planning and customer referrals, providing a structured
and transparent marketing framework while also allowing Core to strike offtake agreements directly and refer
customers to Glencore.
Proposed Divestment of Gold Assets
During the quarter, Core announced it is spinning out its gold and non-lithium tenements through a share sale
agreement (SSA) signed with Axiant Resources Limited for the sale of all the shares (Divestment) in two wholly
owned subsidiaries.
The spin-out will enable Core to focus on the Finniss and the exploration and development of its other lithium
assets, while retaining exposure to the assets and gold price through the ownership of 20 million ordinary shares
in Axiant (Axiant Shares) and up to 20 million performance rights (Performance Rights), as consideration for
the acquisition of the subsidiaries.
Through the SSA, Axiant will acquire gold and non-lithium tenements and mineral rights for exploration projects
located in the Northern Territory and South Australia (the Assets), including the Shoobridge Gold Project.
Axiant intends, subject to market conditions and ASX approval, to undertake an initial public offering (IPO) of
Axiant Shares, under a prospectus, to raise between A$8 million (Minimum Subscription) and A$10 million
(Maximum Subscription) (before costs) at an issue price of A$0.20 per Axiant Share, and to apply for admission
to the official list of the ASX. The IPO will include a priority offer to existing eligible Core shareholders.
Axiant expects to lodge the prospectus with the Australian Securities and Investments Commission (ASIC) in July.
Following completion of the IPO, Core will retain an initial 33% shareholding in Axiant at the Minimum Subscription
and approximately 29% at the Maximum Subscription, on an undiluted basis.
The proposed Divestment of the Subsidiaries enables Core to continue to focus on its primary business, the
operation of Finniss and the exploration and development of its other lithium assets. Core will retain lithium rights
across several of the lithium tenements within some of the Assets.
18 Refer to ASX announcement “Sale of 20,000 tonnes of Lithium Fines” on 30 April 2026 and “Second Sale of Lithium Fines” on 10 June 2026.
19 Refer to ASX announcement " FID Approved and Funding Secured for Finniss Restart” on 18 March 2026 for further information.
corelithium.com.au
10
Board Changes
Core’s Chair, Mr Greg English, retired from the Board on 30 June 2026, coinciding with his appointment as Chair
of Axiant. His tenure represented a highly successful 16 year term at Core as Chair, overseeing early exploration
initiatives, the commencement of open pit mining and ore processing at Finniss in 2021, and more recently, the
completion of a A$307 million funding package, and the recommencement of mining operations.
The Board has appointed existing non-executive director Mr Malcolm McComas as the new Chair of Core,
effective from 30 June 2026. In addition, the Board has commenced a process to identify an additional new
director, as part of an ongoing board renewal process.
General Meeting of Shareholders
A General Meeting of Shareholders was held on 5 May 2026 to consider and approve, among other things, the
tranches of the funding package subject to shareholder approval. All resolutions put to the meeting were passed
on a poll.
Other disclosures
As at 30 June 2026, Core had the following capital structure:
• 3,236,801,664 ordinary shares
• 34,624,913 unquoted performance rights
• 6,500,000 unquoted options
• 25,926,821 unquoted convertible notes
Core’s Appendix 5B includes an amount of A$119k in item 6.1. The amount in item 6.1 represents director fees
paid to entities nominated by the Company’s directors.
Core confirms that it is not aware of any new information or data that materially affects the exploration results,
exploration targets, Mineral Resource Estimate (MRE) and Ore Reserve Estimate (ORE) included in this
announcement as cross referenced in the body of this announcement, and that all technical parameters and
material assumptions underpinning the MRE, ORE and production target and forecast financial information
derived from the production target continue to apply and have not materially changed. The Company confirms
that the form and context in which the Competent Person’s findings are presented have not been materially
modified from the original announcements.
Important Information
This announcement may reference forecasts, estimates, assumptions, and other forward-looking statements.
Although the Company believes that its expectations, estimates and forecast outcomes are based on reasonable
assumptions, it cannot assure that they will be achieved. They may be affected by various variables and changes
in underlying assumptions subject to risk factors associated with the nature of the business, which could cause
results to differ materially from those expressed in this announcement. The Company cautions against reliance
on any forward-looking statements in this announcement.
Webcast
The Company will host an accompanying webcast on 15 July 2026, commencing at 8:00am (AWST) / 10:00am
(AEST)
To listen to the webcast presentation live, please click the link and register your details: Webcast Registration
A recording of the webcast will be available on the Company’s website www.corelithium.com.au following the
conclusion of the webcast.
corelithium.com.au
11
Tenements
Tenement number Tenement name Interest at the end
of Quarter
Changes during
the Quarter
South Australia
EL 6038 Mt Freeling 100% None
EL 6111 Yerelina 100% None
Northern Territory
EL 26848 Walanbanba 100% None
EL 28029 White Range East 100% None
EL 28136 Blueys 100% None
EL 29580 Jervois East 100% None
EL 29581 Jervois West 100% None
EL 29698 Finniss 100% None
EL 29699 Bynoe 100% None
EL 30012 Bynoe 100% None
EL 30015 Bynoe 100% None
EL 31058 Barrow Creek 100% None
EL 31126 Zola 100% None
EL 31127 Ringwood 100% None
EL 31139 Anningie West 100% None
EL 31140 Anningie South 100% None
EL 31145 Barrow Creek North 100% None
EL 31146 Barrow Creek South 100% None
EL 31271 Bynoe 100% None
EL 31279 Sand Palms 100% None
EL 31407 Shoobridge 100% None
EL 31886 Adelaide River 100% None
EL 32205 Finniss Range 100% None
EL 32392 Ivy 100% None
EL 32396 Murray Creek 100% None
EL 33932 Bloodwood 100% None
EL 33933 West Dam 100% None
EL 34075 Douglas 100% None
.
corelithium.com.au
12
Tenements(cont.)
Tenement number Tenement name Interest at the end
of Quarter
Changes during
The Quarter
Northern Territory
EMP 28651 Observation Hill (Extractive Lease) 100% None
ML 29912 Saffums 100% None
ML 29914 Labelle 100% None
ML 29985 Angers North 100% None
ML 31654 Annie/Old Crusher 100% None
ML 31726 Grants Mineral Lease 100% None
ML 32074 Observation Hill (Ancillary Lease) 100% None
ML 32278 Grants Dam (Ancillary Lease) 100% None
ML 32346 BP33 Mineral Lease 100% None
MLN16 Bynoe 100% None
MLN813 Bilatos 100% None
MLN1148 Centurian 100% None
Note: Tenement register does not yet reflect Charger and Axiant agreements outlined above, which are expected to take effect during the
September quarter subject to satisfaction of applicable conditions and required approvals.
This announcement has been approved for release by the Core Lithium Board.
For further information, please contact:
Investor Enquiries
Paul Brown
Managing Director
Core Lithium Ltd
+61 8 8317 1700
info@corelithium.com.au
Media enquiries
Cameron Morse
Senior Managing Director
FTI Consulting
+61 433 886 871
cameron.morse@fticonsulting.com
About Core
Core Lithium Ltd (ASX: CXO) (Core or Company) is an Australian hard-rock lithium company that owns the
Finniss Lithium Operation on the Cox Peninsula, south-west and 88km by sealed road from the Darwin Port,
Northern Territory. Core's vision is to generate sustained value for shareholders from critical minerals exploration
and mining projects underpinned by strong environmental, safety and social standards.
For further information about Core and its projects, visit www.corelithium.com.au.
corelithium.com.au
13
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Core Lithium Ltd
ABN
Quarter ended (“current quarter”)
80 146 287 809 30 June 2026
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(12 months)
$A’000
1. Cash flows from operating activities
1.1 Receipts from customers 16,241 16,241
1.2 Payments for
exploration & evaluation - -
development - -
production (987) (987)
staff costs (2,468) (9,655)
administration and corporate costs (8,194) (14,276)
care and maintenance (216) (2,545)
technical study costs - (2,698)
royalties - (2,000)
1.3 Dividends received (see note 3) - -
1.4 Interest received 1,642 2,774
1.5 Interest and other costs of finance paid (308) (974)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other - crushing contract payment - (3,230)
Other - offtake agreement payment - (3,737)
1.9 Net cash from / (used in) operating
activities
5,710 (21,087)
2. Cash flows from investing activities
2.1 Payments to acquire or for:
entities - -
tenements - -
property, plant and equipment (276) (6,612)
exploration & evaluation (420) (2,192)
investments - (76)
other non-current assets - mine
development
(15,208) (15,208)
2.2 Proceeds from the disposal of:
entities - -
tenements 715 4,002
property, plant and equipment - -
investments - -
other non-current assets - -
2.3 Cash flows from loans to other entities
2.4 Dividends received (see note 3) - -
corelithium.com.au
14
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(12 months)
$A’000
2.5 Other - Net (payments) for security bond 160 (1,821)
2.6 Net cash from / (used in) investing
activities
(15,029) (21,907)
3. Cash flows from financing activities
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities) 67,273 174,931
3.2 Proceeds from issue of convertible debt
securities
37,033 37,033
3.3 Proceeds from exercise of options - 448
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(4,861) (10,739)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other - payment of lease liabilities (105) (539)
3.10 Net cash from / (used in) financing
activities
99,340 201,134
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
91,606 23,486
4.2 Net cash from / (used in) operating activities
(item 1.9 above)
5,710 (21,087)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(15,029) (21,907)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
99,340 201,134
4.5 Effect of movement in exchange rates on
cash held
200 201
4.6 Cash and cash equivalents at end of
period
181,827 181,827
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 181,827 91,606
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
181,827 91,606
corelithium.com.au
15
6. Payments to related parties of the entity and their associates Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
119
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a
description of, and an explanation for, such payments.
7. Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the
entity.
Add notes as necessary for an
understanding of the sources of finance
available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (convertible note) 37,033 37,033
7.4 Total financing facilities 37,033 37,033
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing facilities
have been entered into or are proposed to be entered