September Quarterly Report Presentation
Released
Released
Announcement PDF
September Quarter
FY27
14 OCTOBER 2026
Important and Cautionary Notes
2
This presentation has been prepared by Core Lithium Ltd (“Core”, “Company”) and provides a general overview of the
Company and its strategy.
This presentation does not purport to be all-inclusive or to contain all the information that you or any other party may
require to evaluate the prospects of the Company. None of the Company, any of its related bodies corporate or any of
their representatives assume any responsibility for, or makes any representation or warranty, express or implied, with
respect to the accuracy, reliability or completeness of the information contained in this presentation and none of
those parties have or assume any obligation to provide any additional information or to update this presentation. The
information in this presentation should be read in conjunction with Core’s other periodic and continuous disclosure
announcements lodged with the Australian Securities Exchange (ASX), which are available at www.asx.com.au.
To the fullest extent permitted by law, the Company, its respective affiliates and representatives, related bodies
corporate, officers, employees, partners, agents and advisers make no representation or warranty (express or implied)
as to the currency, accuracy, reliability, reasonableness or completeness of the information in this presentation and
expressly disclaims all responsibility and liability for any loss or damage arising in respect of your reliance on the
information contained in this presentation (including your reliance on the accuracy, completeness or reliability of that
information), or any errors in or omissions from this presentation, including any liability arising from negligence.
The Finniss Lithium Operation as described in this presentation as being in a state of operational readiness, and
potential investors should understand that mineral exploration, development and mining are high-risk undertakings.
There is no guarantee that the Finniss Lithium Operation can be economically exploited in the future.
This document contains statements which may be in the nature of forward-looking statements. No representation or
warranty is given, and nothing in this presentation or any other information made available by the Company or any
other party should be relied upon as a promise or representation, as to the future condition of the respective
businesses and operations of the Company.
Competent Person Statements
The Mineral Resources and Ore Reserves underpinning the production target and forecast financial information in this
announcement have been prepared by competent persons in accordance with the requirements of the JORC code.
Core confirms that it is not aware of any new information or data that materially affects the exploration results,
exploration target, mineral resource estimate and ore reserve estimate included in this announcement as cross
referenced in the body of this announcement and that all technical parameters underpinning the Mineral Resources,
Ore Reserves, production target and forecast financial information derived from the production target continue to
apply and have not materially changed. The announcement references the previously reported Mineral Resource
Estimates and Ore Reserve Estimates; “Finniss Mineral Resource Increased by 58%” on 11 April 2024, “Lithium Ore
Reserve Updated” on 25 September 2024, “Updated Finniss Lithium Operation Reserve and Resource” on 14 May 2025,
“Updated Ore Reserve at Carlton” on 10 September 2025 and “Updated Grants Mine Plan and Ore Reserve” on 10
November 2025. The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the original announcements related to previously reported
exploration results, exploration target, Mineral Resource Estimates and Ore Reserve Estimates.
Currency
Unless otherwise stated, all cashflows are in Australian dollars, are undiscounted and are in real terms (not subject to
inflation/escalation factors).
Forward‐looking Statements
Generally, this forward-looking information can be identified by the use of forward-looking terminology such as
‘outlook’, ‘anticipate’, ‘project’, ‘target’, ‘likely’,’ believe’, ’estimate’, ‘expect’, ’intend’, ’may’, ’would’, ’could’, ’should’,
’scheduled’, ’will’, ’plan’, ’forecast’, ’evolve’ and similar expressions. Persons reading this release are cautioned that such
statements are only predictions, and that the Company’s actual future results or performance may be materially
different. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that
may cause the Company’s actual results, level of activity, performance or achievements to be materially different from
those expressed or implied by such forward-looking information. Forward-looking information is developed based on
assumptions about such risks, uncertainties and other factors set out herein, including but not limited to general
business, economic, competitive, political and social uncertainties; the actual results of current exploration,
development and construction activities; conclusions of economic evaluations; changes in project parameters as plans
continue to be refined; future prices of lithium; possible variations of ore grade or recovery rates; failure of plant,
equipment or processes to operate as anticipated; accident, labour disputes and other risks of the mining industry;
and delays in obtaining governmental approvals or financing or in the completion of development or construction
activities. This list is not exhaustive of the factors that may affect forward-looking information. These and other factors
should be considered carefully, and readers should not place undue reliance on such forward-looking information.
The Company disclaims any intent or obligations to or revise any forward-looking statements whether as a result of
new information, estimates, or options, future events or results or otherwise, unless required to do so by law.
Statements regarding plans with respect to the Company’s mineral properties may contain forward-looking
statements in relation to future matters that can be only made where the Company has a reasonable basis for making
those statements.
Past Performance
Past performance information given in this presentation is given for illustrative purposes only and should not be relied
upon as (and is not) an indication of future performance.
Finniss Lithium Operation
3
Long life, fully funded operation with established infrastructure and expansion optionality
~20 year
TOTAL PROJECT MINE LIFE1
1.2 Mtpa
THROUGHPUT1
257 ktpa
SC5 PRODUCTION2
$635/t
SC5 UNIT COST3
$157m
RESTART CAPITAL REMAINING4
$244m
AVAILABLE FUNDING5
GRANTS OPEN PIT
PRODUCING
BP33 UNDERGROUND
DEVELOPMENT
CARLTON
ORE RESERVE
BLACKBEARD
EXPLORATION
1 3b
3a
2
FINNISS LITHIUM OPERATION
1. Refer to ASX announcement “FID Approved and Funding Secured for Finniss Restart” on 18 March 2026 for further information
2. Nameplate production. Equivalent to 214ktpa of SC6 concentrate (6.0% Li₂O equivalent basis)
3. Unit cost calculated at SC5 FOB, ex-royalties. Represents steady state unit costs during the period where BP33 at full capacity. Equivalent to SC6 unit cost $762/t
4. Restart capital inclusive of contingency
5. Available funding includes cash as at 30 September 2026, undrawn Tranche 2 of Senior Secured loan and receivables
September Quarter Highlights
4
Plant commissioning underway, first concentrate production achieved and BP33 development progressing to plan
Refer to ASX announcement “Quarterly Activities and Cashflow Report” on 14 October 2026 for further information
Corporate
Strong financial position with
$200 million of cash at
30 September 2026
Tranche 2 convertible note
funds of $62 million and
Tranche 1 senior secured
facility funds of $36 million
received in the quarter
Tranche 2 of senior secured
facility remains undrawn
(~$35 million)
Operations
Mining and ore stock build
progressing in line with plan
Initial DMS plant upgrades
completed
First spodumene
concentrate produced at
Finniss
DMS plant commissioning
and optimisation activities
continuing
Sales and
Marketing
Logistics chain fully
operational
Second and third shipments
of stockpiled lithium fines
completed through Darwin
Port
Stockpile sales generated
~$38.5 million of revenue in
CY26
Offtake process ongoing
Exploration
High-grade drill results at
BP33 confirming
mineralisation beyond the
current Mineral Resource
Estimate
Three additional holes to be
drilled at BP33
Blackbeard drilling underway
to support a maiden Mineral
Resource Estimate
BP33 underground
development advancing,
with first development ore
on track for mid-CY27
Key surface infrastructure
works advancing
$157 million restart capital
remaining including
contingency
Development fully funded
through to steady state
production in mid-CY2028
Development
On track for steady state production in 2028
5
Key operational and development milestones tracking to schedule
Funding
and FID
Key mining
contracts for
Grants mining
and BP33
development
awarded
March
2026
Q2
CY26
Q2
CY26
Q3
CY26
H1
CY27
Mid
CY27
Mid
CY28
Grants open pit
mining
commenced
BP33
underground
decline
development
commenced
Plant
commissioning
and first
concentrate
production
BP33
underground
development
and surface
infrastructure
construction
Grants mining,
production and
shipments
BP33
underground
first
development
ore
BP33
steady state
production of
1.2Mtpa
First
concentrate
shipment
from Grants
Q4
CY26
Significant progress achieved at Grants open pit since FID
6
1
2
3
May 2026
Mining commenced
March 2026
FID
September 2026
Mining ongoing
Grants near-term production platform delivering on plan
• Mining and ore stock build progressing in line with plan
• ~134kt of SC5 product expected from Grants in total, with
first shipment in the December quarter
1
• Additional cash flow from Grants provides additional liquidity
beyond the restart funding package
• Flexibility with processing and shipment timing pending
market conditions
7
Grants is the first step of the staged Finniss restart,
providing near-term production and cash
generation while development of BP33 continues
Mining volumes increasing to build ore stocks during the Quarter
Crusher ore stockpile with ROM pad in the background
1. Refer to the Company’s ASX announcement titled “FID Approved and Funding Secured for Finniss Restart” dated 18 March 2026
Initial brownfields plant upgrades complete
8
Plant throughput capacity to increase
by 20% to 1.2 Mtpa following
completion of targeted upgrades
Reflux classifier installation on schedule for FY27
• Initial plant upgrades completed to
debottleneck the circuit and support improved
liberation, recoveries and throughput including:
• screen refurbishments;
• enhancements in the rolls crusher and tails
thickener circuits;
• improvements to the ferrosilicon distribution
system; and
• consolidation of crushing and DMS plant
operations into a single control room.
• Installation of the reflux classifier circuit, a long
lead time item and the final brownfields
upgrade, is expected to be completed in FY27.
DMS plant brownfields modifications (Left to right) 1. Upgraded rolls crusher screen. 2. Reflux classifier pad. 3. New middlings conveyor
First concentrate produced as commissioning continues
9
First shipment of newly produced concentrate
on track for the December quarter FY27
Initial brownfields plant upgrades complete
• First spodumene concentrate produced from the
upgraded Finniss processing plant
• First production achieved within six months of FID
• Initial upgrades completed to debottleneck the circuit and
support improved liberation, recoveries and throughput
1
• Commissioning focused on optimising plant performance,
operational reliability and progressive throughput ramp-
up
Spodumene production from Grants open pit ore
1. Installation of the reflux classifier circuit, a long lead time item and the final brownfields upgrade, is expected to be completed in FY27.
BP33 underground development advancing on schedule
Key underground development activities in the Quarter included:
• Completion of the underground portal construction, including steel
headcover installation
• Installation and commissioning of:
• temporary mine power generators and transformer
• mine services including HV cable, process water and dewatering
• temporary ventilation fan and ducting
• Shotcreting of boxcut bench surfaces continued with 50% complete
10
Strong development momentum at BP33 continues to de-
risk the pathway to steady-state production.
First development ore on track for mid-CY27
BP33 underground development progress, including box cut remediation, completed portal and temporary
ventilation fan
BP33 momentum continues across surface infrastructure works
BP33 construction activities during the Quarter included:
• Progression of critical ventilation infrastructure works, with piling
activities for the fresh air and return air rises advancing
• Significant advancement of site water management infrastructure,
including construction of water storage facilities, installation of water
distribution pipelines and commissioning of operational water supply
systems
• Completion of wet season preparedness works including erosion and
sediment control infrastructure
• Commencement of earthworks associated with the ROM pad
• Completion of additional dust suppression infrastructure and
associated pipeline installation
• Completion and commissioning of key site infrastructure including
offices, ablutions and contractor mobile maintenance facilities
• Mobilisation of civil contractor for intersection and access road
upgrades
11
Key infrastructure construction progressing in line with the BP33 development plan
Infrastructure works at BP33 (clockwise from top left) 1. Contractor laydown area with mobile maintenance facility 2. Site offices
3. Completed mine water dam cells 4. Ventilation shafts development works
BP33 extensional exploration drilling delivering results
• The first exploration diamond drill hole completed outside the
current BP33 Mineral Resource returned high-grade lithium
mineralisation, including 34.08m @ 2.09% Li₂O from 578.7m and
3.43m @ 2.44% Li₂O from 616.5m
1
• The result was returned from hole NMRD100, which was designed to
test extensions to mineralisation outside the existing BP33 Mineral
Resource Estimate of 10.5Mt @ 1.53% Li₂O
2
• Results reinforce confidence in the size, continuity and quality of the
BP33 orebody and support the potential for future Mineral Resource
growth beyond the current resource boundary
• Follow-up drilling is underway, with 3 additional holes targeting
extensions to mineralisation both down-dip and along strike from
NMRD100 and NMRD085
12
Excellent new high grade lithium results strengthen
confidence in the quality and continuity of the
orebody Figure 1: BP33 Resource and Exploration Target outline3 Figure 2: Geological Cross Section – NMRD085 and NMRD100 at BP33
1. Refer to ASX announcement New High-Grade Lithium Drill Results at BP33” on 11 August 2026
2. Refer to ASX announcements “New High-grade Lithium Drill Results within 20km of Grants” on 6 November 2024 and "Updated Finniss Lithium Project Reserve and Resource” on 14 May 2025
3. The BP33 Exploration Target of between is 3.9Mt and 6.5Mt at a grade of between 1.5% and 1.6% Li2O was released as Updated Finniss Lithium Project Reserve and Resource on 14 May 2025.
The potential quantity and grade of the Exploration Target is conceptual in nature. There has been insufficient exploration to estimate a Mineral Resource and it is uncertain if further exploration
will result in the estimation of a Mineral Resource
Follow-up drilling underway targeting extensions to mineralisation
Blackbeard exploration program ongoing
• The Blackbeard exploration program continued during the
period, designed to support a maiden Mineral Resource Estimate
and further assess its potential as a future source of high-grade
ore feed for Finniss
• Staged and gated diamond-drilling campaign totaling 12,150
metres
• Blackbeard is a high-grade lithium prospect within 20km of
existing processing infrastructure, located on a Mining Lease
(MLN1148)
• High-grade drilling results at Blackbeard could provide
a potential key catalyst for expansion
Blackbeard exploration target: 7-10Mt at 1.5-1.7%1
13
Drilling underway to support a maiden MRE at highest priority growth prospect
The Exploration Target is supported by historical drilling, trenching & exploration
results. The potential quantity & grade of the Exploration Target is conceptual in
nature. There has been insufficient exploration to estimate a Mineral Resource & it is
uncertain if further exploration will result in the estimation of a Mineral Resource1
1. Refer to the Company's ASX announcement titled “Updated Finniss Lithium Project Reserve and Resource” dated 14 May 2025 for further information regarding the exploration target
Exploration program: Diamond drilling campaign underway at Blackbeard
Cashflows reflect operational transition
14
• Funding receipts: $98 million net of fees:
• $62 million from Tranche 2 Convertible Note funding
received from Glencore and Infravia
• $36 million from Tranche 1 Senior Debt Facility received
from Nebari
• Site operating costs: $13 million including open pit mining,
processing, maintenance and site administration
• Capital expenditure: $51 million invested in BP33
underground development and infrastructure construction,
and targeted DMS plant upgrades
• Cash flows reflect the transition to operations, with operating
costs incurred ahead of cash receipts from production
• September Quarter cash flow does not include any revenues
generated from Grants near-term production of ~134kt SC5
product, with first shipment expected in December quarter
Funding receipts increased cash while operating costs began and restart capex accelerated
62
36
(11)
8
(13) (7) (7)
(51)
10
182
200
35 244
0
50
100
150
200
250
300 A$
million
Executing to plan
15
Near-term focus: Plant commissioning | First shipment | BP33 development
COMPLETED
Funding package
Secured
Major contracts
Awarded
Logistics chain
Fully operational
Portal cut
Complete
Initial plant upgrades
Complete
First concentrate
Produced
Stockpiled fines sales
Complete
IN PROGRESS
Grants mining
Ongoing
Plant commissioning
Optimisation ongoing
BP33 decline
Development advancing
BP33 surface infrastructure
Construction
Offtake process
Ongoing
Exploration
Drilling
Production expansion
Studies
UPCOMING
First shipment
December quarter
Reflux classifier
Installation in FY27
Exploration
Results
First BP33 development ore
Mid CY27
Steady state production
Mid CY28
Restart schedule, production plan and capital assumptions remain unchanged since FID
corelithium.com.au
Contact
Core Lithium Ltd
Level 4, 186 St Georges Terrace
Perth WA 6000
E info@corelithium.com.au
This presentation has been approved for release
by the Core Lithium Board
Investor Enquiries
Paul Brown
Managing Director
+61 8 8317 1700
Media Enquiries
Cameron Morse
FTI Consulting
+61 433 886 871
Appendix 1 – JORC Mineral Resource Estimate
17
Mineral Resource
Measured Indicated Inferred Total
Tonnes
(Mt)
Li2O%
Li2O
Contained
Metal (kt)
Tonnes
(Mt)
Li2O%
Li2O
Contained
Metal (kt)
Tonnes
(Mt)
Li2O%
Li2O
Contained
Metal (kt)
Tonnes
(Mt)
Li2O%
Li2O
Contained
Metal (kt)
Grants 1.34 1.48 19.8 0.61 1.49 9.1 0.37 1.27 4.7 2.32 1.45 33.6
BP33 2.85 1.44 41.0 6.51 1.55 101 1.14 1.59 18.1 10.5 1.53 161
Carlton 2.14 1.33 28.5 3.43 1.32 45.3 0.78 1.14 8.9 6.34 1.3 82.6
Lees - - - 4.16 1.18 49.1 7.08 1.12 79.3 11.2 1.14 128
Ah Hoy - - - 1.71 1.2 20.5 2.93 1.38 40.4 4.64 1.31 60.8
Booths - - - 1.84 0.99 18.2 1.4 1.06 14.8 3.24 1.02 33
Penfolds - - - 0.65 1.25 8.1 0.71 1.24 8.8 1.36 1.24 16.9
Hang Gong - - - 1.51 1.18 17.8 1.95 1.14 22.2 3.46 1.16 40.1
Sandras - - - 1.17 0.92 10.8 0.57 0.82 4.7 1.73 0.89 15.4
Bilatos - - - - - - 1.92 1.03 19.8 1.92 1.03 19.8
Seadog - - - - - - 1.41 1.18 16.6 1.41 1.18 16.6
Total 6.33 1.41 89 21.6 1.3 282 20.3 1.18 239 48.2 1.26 608
TSF/Stockpiles - - - 0.31 0.66 2 - - - 0.31 0.66 2.0
Total 6.33 1.41 89 21.9 1.29 283 20.3 1.18 239 48.5 1.26 610
Note: Totals within this table are subject to rounding
Refer to the Company's ASX announcement titled “Finniss Mineral Resource Increased by 58%” on 11 April 2024 and “Updated Finniss Lithium Project Reserve and Resource” dated 14 May 2025 for further information.
Refer to the Company's ASX announcement titled “Updated Grants Mine Plan and Ore Reserve“ dated 10 November 2025 for further information
Appendix 2 – JORC Ore Reserve Estimate
18
Note: Totals within this table are subject to rounding
Refer to the Company's ASX announcement titled “Finniss Mineral Resource Increased by 58%” on 11 April 2024 and “Updated Finniss Lithium Project Reserve and Resource” dated 14 May 2025 for further information.
Refer to the Company's ASX announcement titled “Updated Grants Mine Plan and Ore Reserve“ dated 10 November 2025 for further information
Deposit Category
Ore Tonnes
(Mt)
Li2O (%)
Contained
Li2O (kt)
BP33
Underground
Proved 2.6 1.27 32
Probable 6.7 1.32 89
Total 9.3 1.31 121
Grants
Proved 1.2 1.43 17
Probable 0.3 1.41 5
Total 1.5 1.42 22
Carlton
Proved 1.7 1.19 20
Probable 2.8 1.19 34
Total 4.5 1.19 53
TSF/Stockpiles
Proved - - -
Probable 0.3 0.68 2
Total 0.3 0.68 2
Total
Proved 5.1 1.28 69
Probable 10.1 1.27 129
Total 15.6 1.27 198
Notes
1. Effective date of the Grants Ore Reserves is 30 October 2025.
2. Effective date of the Carlton Ore Reserves is 5 September 2025 (“Updated Ore Reserve at
Carlton” released on 10 September 2025).
3. Effective date of the BP33 and TSF/Stockpiles Ore Reserves is 30 April 2025. (“Updated
Finniss Lithium Project Reserve and Resource” released on 14 May 2025)
4. Ore Reserve Estimates are the total for the Grants, BP33, TSF/Stockpiles and
Carlton Mines.
5. The long-term SC6 Spodumene price used for calculating the financial analysis is
US$1,330/t. The financial analysis has been estimated with assumptions for crushing,
processing and treatment charges, deductions and payment terms, concentrate
transport, metallurgical recoveries, and royalties.
6. The breakeven cut-off Net Smelter Return (NSR) for underground mining at BP33 and
Grants Underground is $110/t NSR and $125/t NSR for Carlton Underground. The cutoff
grade used for estimating Ore Reserve Estimate at Grants Open pit was 0.8%.
7. Measured Mineral Resources were used to estimate Proved Ore Reserves; Indicated
Mineral Resources were used to estimate Probable Ore Reserves.
8. Tonnage and grade estimates include dilution and recovery allowances.
9. The tonnage and grade for TSF/Stockpile is estimated from the operations reconciled
historic monthly production records.
10. The Reserves are defined at the point where the ore is delivered to the
processing plant.
11. The Ore Reserves reported above are not additive to the Mineral Resources.
12. Totals within this table are subject to rounding.