Finniss Funding and Restart Presentation
Released
Released
Announcement PDF
FINNISS RESTART
FUNDING SECURED AND FINAL
INVESTMENT DECISION
18 March 2026
ASX:CXO
NOT FOR RELEASE TO US WIRE SERVICES OR DISTRIBUTION IN THE UNITED STATES
IMPORTANT AND CAUTIONARY NOTES
2
This presentation is dated 18 March 2026 and has been prepared by Core Lithium Ltd (Core or the Company) in
connection with an equity raising by Core comprising an unconditional placement of fully paid ordinary shares in Core
(New Shares) utilising the Company's existing placement capacity under Listing Rule 7.1 (Unconditional Placement)
and a conditional placement of New Shares subject to shareholder approval (Conditional Placement), in each case
to institutional and sophisticated investors (together, the Placement).
This presentation does not constitute an offer to sell, or a solicitation of an offer to buy any securities in any
jurisdiction. The distribution of this presentation and the offer of securities is restricted in jurisdictions outside
Australia. See the section of this presentation captioned “International Offer Jurisdictions” for more information. Any
failure to comply with such restrictions could constitute a violation of applicable securities laws.
Unless otherwise defined in these Important and Cautionary Notes, capitalised terms have the meanings given to
them elsewhere in this presentation.
Acceptance
By attending an investor presentation and/or by briefing, or accepting, accessing or reviewing this presentation, you
accept the terms, conditions and disclaimers herein.
This presentation is provided expressly on the basis that you will carry out your own independent inquiries into the
matters contained in the presentation and make your own independent decisions about the affairs, financial position
or prospects of the Company (having regard to the requirements of all relevant jurisdictions).
Disclaimer
This presentation provides a general overview of the Company and its strategy for information purposes and is a
summary only. This presentation does not purport to be all-inclusive or to contain all the information that a
prospective investor may require in connection with any potential investment in the Company or to evaluate the
prospects of the Company. None of the Company, any of its related bodies corporate or any of their representatives
assume any responsibility for, or makes any representation or warranty, express or implied, with respect to the
accuracy, reliability or completeness of the information contained in this presentation and none of those parties have
or assume any obligation to provide any additional information or to update this presentation. The information in this
presentation should be read in conjunction with Core’s other periodic and continuous disclosure announcements
lodged with the Australian Securities Exchange (ASX), which are available at www.asx.com.au under the Company’s
ticker code (ASX:CXO). Each recipient must make its own independent assessment of the Company and should seek
professional advice before acquiring any New Shares in the Company.
The contents of this presentation is provided as at the date of this presentation (unless otherwise stated) and the
Company reserves the right to update, amend or supplement the information at any time in its absolute discretion
(without incurring any obligation to do so). No party other than the Company has authorised or caused the issue,
lodgement, submission, despatch or provision of this presentation, or takes any responsibility for, or makes or
purports to make any statements, representations or undertakings in this presentation.
Except for any liability that cannot be excluded by law, and to the fullest extent permitted by law, the Company, its
respective affiliates and representatives, related bodies corporate, officers, employees, partners, agents and advisers
(each a Core Party) make no representation or warranty (express or implied) as to the currency, accuracy, reliability,
reasonableness or completeness of the information, opinions or conclusions in this presentation and expressly
disclaims all responsibility and liability for any loss or damage arising in respect of your reliance on the information
contained in this presentation (including your reliance on the accuracy, completeness or reliability of that
information), or any errors in or omissions from this presentation, including any liability arising from negligence. No
Core Party has or assumes any obligation to provide any additional information or to update this presentation.
The Finniss Lithium Project is described in this presentation as being in a particular state of operational readiness,
based on a number of assumptions as detailed in the Restart Study (Study) released by the Company on 14 May 2025
and potential investors should understand that mineral exploration, development and mining are high-risk
undertakings. Refer to the Company's ASX announcement titled “Restart Study Repositions Finniss Operations” dated
14 May 2025 for further information and for a copy of the Study. There is no guarantee that the Finniss Lithium
Project can be economically exploited in the future and investors should have regard to the operational and
development risks set out in the ‘Key Risks’ section of this presentation.
Not a prospectus or disclosure document
Information in this presentation which is attributed to a third-party source has not been checked or verified by the
Company. This presentation is not a prospectus, disclosure document or other offer document under the
Corporations Act 2001 (Cth) (Corporations Act) or under any other law. This presentation will not be lodged with the
Australian Securities and Investments Commission (ASIC) or any other foreign regulator. It is provided for information
purposes and is not an invitation nor offer of New Shares or recommendation for subscription, purchase or sale in
any jurisdiction. Neither this presentation nor any of the information contained herein will form the basis of any
contract or commitment to sell, subscribe for or acquire securities in the Company or any other financial product.
The Placement will be conducted under section 708A of the Corporations Act and will be made available to certain
persons who are “professional” or “sophisticated” investors as defined in subsections 708(8) and 708(11) of the
Corporations Act.
Distribution outside Australia
Distribution or release of this presentation outside Australia may be restricted by law. This presentation may not be
distributed in any jurisdiction except in accordance with applicable legal requirements. Persons who come into
possession of this document should observe any such restrictions as any non-compliance could contravene
applicable securities laws. Please refer to the section of this presentation captioned “International offer restrictions"
for more information.
Not for release to US wire services or distribution in the United States
This presentation has been prepared for publication in Australia and may not be released to US wire services or
distributed in the United States. This presentation does not constitute an offer to sell, or a solicitation of an offer to
buy, securities in the United States or any other jurisdiction. Any securities described in this presentation have not
been, and will not be, registered under the US Securities Act of 1933 (US Securities Act) and may not be offered or
sold in the United States except in transactions exempt from, or not subject to, the registration requirements of the
US Securities Act and applicable US state securities laws.
IMPORTANT AND CAUTIONARY NOTES
3
Investment and other risks
There are a number of risks specific to the Company and of a general nature which may affect the future operating
and financial performance of the Company and the value of an investment in the Company, including and not limited
to the Company's capital requirements, the potential for shareholders to be diluted, risks associated with the
reporting of Mineral Resources and Ore Reserves estimates, budget risks, development risk and operational risk. An
investment in New Shares is subject to known and unknown risks, some of which are beyond the control of the
Company. The Company does not guarantee any particular rate of return or the performance of the Company.
Investors should have regard to the risk factors outlined in this presentation under the section titled “Key Risks” when
making their investment decision.
Not investment or financial product advice
The information contained in this presentation is for information purposes only and does not constitute investment
advice or financial product advice (nor taxation, accounting or legal advice). Each recipient of this presentation should
make its own enquiries and investigations regarding all information in this presentation including, but not limited to,
the assumptions, uncertainties and contingencies which may affect future operations of the Company and the impact
that different future outcomes might have on the Company. Information in this presentation is not intended to be
relied upon as advice to investors or potential investors for making an investment decision. The Company prepared
this presentation without taking account of any person’s individual investment objectives, financial situation or
particular needs. Before making an investment decision, prospective investors should consider the appropriateness
of the information having regard to their own investment objectives, financial situation and needs and seek legal,
accounting and taxation advice appropriate to their jurisdiction.
Each recipient of this presentation is solely responsible for forming their own opinions and conclusions on such
matters and the market and for making their own independent assessment of the information provided. Any
investment decision by a recipient must be made solely on the basis of their own enquiries. No reliance may be
placed for any purpose whatsoever on the information included in this presentation or on its accuracy or
completeness.
The Company is not licensed to provide investment or financial product advice in respect of its securities (including
New Shares). Cooling off rights do not apply to the acquisition of New Shares.
JORC Code
It is a requirement of the ASX Listing Rules that the reporting of ore reserves and mineral resources in Australia
comply with the 2012 Joint Ore Reserves Committee’s Australasian Code for Reporting of Mineral Resources and Ore
Reserves (JORC Code). Investors outside Australia should note that while Ore Reserve and Mineral Resource
estimates of the Company in this presentation comply with the JORC Code (such JORC Code-compliant ore reserves
and mineral resources being "Ore Reserves" and "Mineral Resources" respectively), they may not comply with the
relevant guidelines in other countries and, in particular, do not comply with (i) National Instrument 43-101 (Standards
of Disclosure for Mineral Projects) of the Canadian Securities Administrators (the "Canadian NI 43-101 Standards"); or
(ii) Item 1300 of Regulation S-K, which governs disclosures of mineral reserves in registration statements filed with the
US Securities and Exchange Commission. Information contained in this presentation describing mineral deposits may
not be comparable to similar information made public by companies subject to the reporting and disclosure
requirements of Canadian or US securities laws. You should not assume that quantities reported as “resources” will
be converted to reserves under the JORC Code or any other reporting regime or that the Company will be able to
legally and economically extract them.
Competent Person Statements
This presentation includes estimates of Mineral Resources and Ore Reserves as well as production targets and
forecast financial information. Core has previously reported these estimates in ASX Announcements “Updated Finniss
Lithium Project Ore Reserve and Mineral Resources” on 14 May 2025, “Restart Study Repositions Finniss Operations”
on 14 May 2025, “Updated Ore Reserve at Carlton” released on 10 September 2025, “Updated Grants Mine Plan and
Ore Reserve” on 10 November 2025 and “Final Investment Decision and Funding Secured for the Restart of the Finniss
Lithium Operation” on 18 March 2026.
Core confirms that it is not aware of any new information or data that materially affects the results and production
target included in the previous announcements (as may be cross referenced in the body of this presentation) and that
all material assumptions and technical parameters underpinning the Mineral Resources, Ore Reserves, production
target and forecast financial information derived from the production target continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the original announcements and that the information in the
announcement relating to exploration results is based upon, and fairly represents, the information and supporting
documentation prepared by the named Competent Persons.
Production Target
The Study (as defined above) includes a production target of 214ktpa spodumene concentrate (6%) equivalent, which
contains approximately 12.9% of Inferred Mineral Resources. An Inferred Mineral Resource has a lower level of
confidence than an Ore Reserve or a Measured and Indicated Mineral Resource, and there is no certainty that further
exploration work will result in the conversion of the Inferred mineralisation into an Ore Reserve or Measured or
Indicated Mineral Resource or that the production target itself will be realised.
The Company confirms that it is not aware of any new information or data that materially affects the production
target information or the forecast financial information derived therefrom included in the Study. The Company
confirms that all material assumptions underpinning the production target or the forecast financial information
derived therefrom continue to apply and have not materially changed. The Company confirms that the form and
context in which the Competent Person’s findings are presented have not been materially modified from the Study.
Currency
Unless otherwise stated, all cashflows are in Australian dollars, are undiscounted and are in real terms (not subject to
inflation/escalation factors).
Effect of rounding
A number of figures, amounts, percentages, estimates, calculations of value and fractions in this presentation are
subject to the effect of rounding. Accordingly, the actual calculation of these figures may differ from the figures set
out in this presentation.
IMPORTANT AND CAUTIONARY NOTES
4
Determination of eligibility
Investors acknowledge and agree that determination of eligibility of investors for the purposes of the Placement is
determined by reference to a number of matters, including the legal and regulatory requirements, logistical and
registry constraints and the discretion of one or more Core Parties. Each Core Party, its respective related bodies
corporate or any of their representatives disclaim any duty or liability (including without limitation, any liability arising
from fault or negligence on the part of any person) in respect of that determination and the exercise or otherwise of
that discretion, to the maximum extent permitted by law. Each Core Party may rely on information provided by or on
behalf of institutional or sophisticated investors in connection with managing and conducting the Placement without
independently verifying that information and each Core Party does not assume responsibility for the currency,
accuracy, reliability or completeness of that information.
Pro-forma financial information
Investors should be aware that this presentation contains pro-forma financial information and certain other financial
information and measures that are “non IFRS financial information” under Regulatory Guide 230: ‘Disclosing non IFRS
financial information’ published by ASIC and are not recognised under Australian Accounting Standards (AAS) and
International Financial Reporting Standards (IFRS). The non IFRS financial information financial measures do not have
a standardised meaning prescribed by the applicable AAS or IFRS, and therefore, may not be comparable to similarly
titled measures presented by other entities, nor should they be construed as an alternative to other financial
measures determined in accordance with the applicable AAS or IFRS. This includes measures such as cash operating
costs, EBITDA, NPV and project payback. Although the Company believes the non-IFRS financial information and
financial measures provide useful information to users in measuring the financial performance and condition of the
Company, investors are cautioned not to place undue reliance on any non-IFRS financial information or financial
measures included in this presentation.
This presentation contains pro forma financial information reflecting the Placement. The pro forma financial
information provided in this presentation is for illustrative purposes only and is not represented as being indicative of
the Company's (or anyone else's) views on the Company's future financial position and/or performance.
Forward‐looking Statements
This presentation contains forward-looking statements and comments about future matters. Generally, this forward-
looking information can be identified by the use of forward-looking terminology such as ‘outlook’, ‘anticipate’, ‘project’,
‘target’, ‘likely’,’ believe’, ’estimate’, ‘expect’, ’intend’, ’may’, ’would’, ’could’, ’should’, ’scheduled’, ’will’, ’plan’, ’forecast’,
’evolve’ and similar expressions.
Persons reading this presentation are cautioned that such statements are only predictions, and that the Company’s
actual future results or performance may be materially different. Forward-looking information is subject to known
and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity,
performance or achievements to be materially different from those expressed or implied by such forward-looking
information. Forward-looking information is developed based on assumptions about such risks, uncertainties and
other factors set out herein, including but not limited to general business, economic, competitive, political and social
uncertainties; the actual results of current exploration, development and construction activities; conclusions of
economic evaluations; changes in project parameters as plans continue to be refined; future prices of lithium;
possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated;
accident, labour disputes and other risks of the mining industry; and delays in obtaining governmental approvals or
financing or in the completion of development or construction activities. This list is not exhaustive of the factors that
may affect forward-looking information. These and other factors should be considered carefully, and readers should
not place undue reliance on such forward-looking information. The Company disclaims any intent or obligations to or
revise any forward-looking statements whether as a result of new information, estimates, or options, future events or
results or otherwise, unless required to do so by law. Statements regarding plans with respect to the Company’s
mineral properties may contain forward-looking statements in relation to future matters that can be only made
where the Company has a reasonable basis for making those statements.
Past Performance
Past performance information given in this presentation is given for illustrative purposes only and should not be
relied upon as (and is not) an indication of future performance.
Authorisation
This presentation has been authorised for release by the Board of Core Lithium Ltd.
1. Executive
Summary
5
KEY INVESTMENT HIGHLIGHTS
6
FID Taken, Restart Ready
Fully-Financed and
Holistic Solution for
Finniss
Experienced
Management Team
Enhanced by High-Quality
Strategic Partners
Accelerated Restart
Timing with Supportive
Lithium Price Tailwinds
Attractive Through-cycle
Cost Position
• Strong returns with 2 to 3-year payback across various prices1
• Robust long term production profile with 20-year mine life and 214ktpa1 spodumene concentrate (6%) equivalent (SC6) nameplate production
• Resource and plant capacity expansion, together with high grade drilling results at Blackbeard5, highlight additional upside to FID case
• Restart fully funded through a diversified financing package (excluding costs), comprising;
− US$70 million convertible notes and US$50 million senior secured loan facility
− A$120 million equity raising, comprising an institutional unconditional placement2 and a conditional placement3
• Marketing agreement with Glencore delivers certainty of product placement while retaining full offtake flexibility
• Delivers overall funding at an attractive cost of capital and lower dilution, maintaining greater upside for existing shareholders
• Competitive unit operating cost of A$762/t FOB and attractive EBITDA margin of 48%1
• Mining method and processing leverage the underground ore body at BP33 whilst driving step-change efficiency and a structurally lower cost profile5
• Competitive cost position driven by improvements in mining productivity, flowsheet simplification and 100% infrastructure ownership model
• Accelerated restart to deliver near term production, offering investors unique brownfields exposure, supported by a favourable pricing backdrop and
limited execution risk
• Significant upside with >2Mtpa crushing capacity5 and significant Ore Reserves and exploration potential providing a pathway to increase scale
• Robust demand fundamentals in the medium and long term driven by chemical converter demand for spodumene concentrate, underpinning sustained
spodumene consumption4
• Proven management team with deep experience in lithium mining operations, project delivery and capital markets
• Strategic partnerships with Glencore, InfraVia and Nebari enhance project certainty through secured product placement, long-term aligned capital and
tailored debt funding to support restart and ramp-up5
• Alignment with well-capitalised, long-term strategic partners supporting execution, funding certainty and operational outcomes
1
2
3
4
5
1. Based on 6% spodumene concentrate price of US$1,500/t CIF for the base case and US$2,200/t CIF for the 2-year payback, an exchange
rate of AUD/USD 0.7000 and nameplate throughput of 1.2Mtpa. Payback calculated from first capex spend in January 2026
2. Unconditional placement utilising the Company’s existing 15% placement capacity under Listing Rule 7.1
3. Conditional placement is subject to shareholder vote. Financing solution subject to completion of the conditional placement, stated “Key
Risks” and no change to capital commitments or material interest rate rises
4. Wood Mackenzie Global Lithium Investment Horizon Outlook, December 2025
5. Refer to the Company's ASX announcements titled “Restart Study Repositions Finniss Operations” dated 14 May 2025, "Updated Grants
Mine Plan and Ore Reserve" dated 10 November 2025 and "Final Investment Decision and Funding Secured for the Restart of the Finniss
Lithium Operation" dated 18 March 2026 for further information
A fully funded restart underpinned by strong economics, long mine life with growth potential and clear pathway
to execution
7
FID TAKEN, RESTART READY4
1
Strong Project Returns
A$1,104 million
NPV8 Pre-tax
A$837 million
NPV8 Post-tax
3-year2
Payback Period
76.5%
IRR Unlevered Post-tax
A$1.7 billion
Cash Generation
(US$1,500/t spodumene
concentrate price)
Robust Long Term Production Profile
20-year
Mine Life
214 ktpa
Nameplate Production
SC6 eq.
78%5
Average Global Recoveries
Low costs drive margins and price cycle resilience
US$533/t
(A$762/t)
Unit Cost1
(FOB, SC6 eq. ex-royalties)
A$208 million
Finniss Restart
Capital3
48%2
EBITDA Margin
Project demonstrates robust metrics across various commodity price scenarios
1. Represents unit costs during the period where BP33 is at full capacity (~1.2Mtpa)
2. Based on 6% spodumene concentrate price of US$1,500/t CIF and an exchange rate of AUD/USD 0.7000. Payback calculated from first capex
spend in January 2026
3. Capital inclusive of contingency
4. Refer to the Company's ASX announcements titled “Restart Study Repositions Finniss Operations” dated 14 May 2025, "Updated Grants Mine
Plan and Ore Reserve" dated 10 November 2025 "Final Investment Decision and Funding Secured for the Restart of the Finniss Lithium
Operation" dated 18 March 2026 for further information
5. Average Global recovery once the Reflux Classifier circuit is operational
Free Cashflow of
A$1.7 billion at
US$1,500/t CIF
spodumene
concentrate price
Potential for
significant upside
to be realised at
spot prices
8
Strategic funding and equity raise deliver full restart certainty with a disciplined, diversified capital structure
Sources and Uses
Financing Package (excluding Costs)
1. Based on exchange rate of AUD/USD $0.7074
2. Amortisation holiday for first 18-months
3. Contingency is 15% of restart capital
4. Forecasted cash at 31 March 2026
5. Spodumene sales expected to be realised in the June quarter 2026
6. Total sources and uses of funds subject to completion of the conditional placement, stated “Key Risks” and no change to capital commitments
or material interest rate rises
7. Refer to slide 16 for further details
8. The upfront component of the convertible notes will be issued after the unconditional placement closes and 15 business days after satisfaction
of certain conditions (including closing an equity raise of US$25 million, that will be satisfied upon closing the unconditional placement) and the
deferred component of convertible notes will be delivered following the conditional placement and remains subject to shareholder approval
and Foreign Investment Review Board (FIRB) Approval. The senior secured loan is inter-conditional to the tranche 2 notes and therefore remains
subject to shareholder approval and FIRB Approval
Senior Secured Loan
Equity Raise
Convertible Notes
• 6-year US$70 million convertible notes from Glencore (US$20
million) and InfraVia (US$50 million)
• Issuer early-redemption right after 2-years if the volume
weighted average price > 160% of conversion price
• Structured to support funding certainty and balance-sheet
flexibility through the restart phase
• Aligned with marketing and strategic partnership objectives
• 4-year senior secured loan financing provided by Nebari
• US$50 million structured as tranche 1 of US$25 million and
tranche 2 of US$25 million (undrawn)
• No amortisation during ramp-up until steady state production
is achieved2
• Equity raising of A$120 million to support restart funding and
balance sheet strength
• Unconditional placement utilising the Company's existing 15%
placement capacity
• Conditional placement subject to shareholder approval
Uses of Funds7 Total A$ million1
Restart capital with contingency3 208
General corporate purposes and transaction costs 69
Growth and exploration 30
Total Uses 307
Senior secured loan – tranche 2 (undrawn) 35
Sources of Funds (excluding costs) Total A$ million1
Convertible notes 99
Senior secured loan – tranche 1 35
Equity raising 120
Cash4 41
Proceeds from spodumene sales5 11
Total Sources 307
Senior secured loan – tranche 2 (undrawn) 35
FINANCING SECURED6,8
2
-
1,000
2,000
3,000
4,000
5,000
6,000
2022 2023 2024 2025 2026
Unit Operating Cost A$762/t1 (eq. ~US$533/t3)
SC62
Unit Operating Cost1,4
9
• Potential EBITDA margin of 48% and 58% at a commodity price
of US$1,500/t and US$2,200/t respectively
• Increased mining productivity driven by majority underground
mining
• Optimised mining costs exploiting large, continuous stopes
• Optimised mine plan, simplified flowsheet and increased
throughput
• Lower processing cost model with 100% infrastructure
ownership
• A structurally low-cost mine plan built to withstand the price
cycles, underpinned by bulk stoping, strong recoveries and
simple processing and logistics
Source: Bloomberg
1. Unit operating costs of A$762/t FOB based on nameplate throughput of 1.2Mtpa
2. Benchmark Mineral Intelligence Spodumene 6% Australia FOB
3. Based on the exchange rate of AUD/USD 0.7000
4. Unit operating cost (FOB excluding royalties) includes mining, processing, haulage, port charges, and site-based general and
administration costs. It is calculated on an SC6 equivalent basis
5. Refer to the Company's ASX announcements titled “Restart Study Repositions Finniss Operations” dated 14 May 2025, "Updated Grants
Mine Plan and Ore Reserve" dated 10 November 2025 "Final Investment Decision and Funding Secured for the Restart of the Finniss
Lithium Operation" dated 18 March 2026 for further information
Low Operating Costs Driven by Production Optimisation5
Lithium SC6 Price FOB Australia (US$/t)
3 ATTRACTIVE COST POSITION
Significant headroom across the commodity price cycle
Funding and
FID
Commence
restart capital
deployment
and mobilisation
activities
Q1
CY2026
Q2
CY2026
Q2
CY2026
Q3/4
CY2026
CY2026-
CY2027
Mid
CY2027
Mid
CY2028
Grants open pit
begins with
concurrent BP33
box cut works
BP33 decline
progresses with
plant starting
and the first
concentrate
shipment
Progressive spend
across pre-
production mining
development,
civils, plant upgrades,
box cut works,
ventilation systems,
and supporting
infrastructure
BP33 underground
achieves first ore,
marking the end of
the pre-production
period for BP33
BP33 reaches full
production rate of
1.2Mtpa
10
RESTART TIMELINE1,2
4
Staged restart pathway delivers near-term production with a disciplined transition to underground operations
1. Illustrative purposes only. Timing is based on current estimates to complete scheduled work and remains subject to change and various conditions (including on-time delivery by counterpart