2026 AGM Presentation
Released
Released
Announcement PDF
2026 Annual General Meeting
Presentation
25 NOVEMBER 2026
ASX:CXO
Important and Cautionary Notes
2
This presentation has been prepared by Core Lithium Ltd (“Core”, “Company”) and provides a general overview of the
Company and its strategy.
This presentation does not purport to be all-inclusive or to contain all the information that you or any other party may
require to evaluate the prospects of the Company. None of the Company, any of its related bodies corporate or any of
their representatives assume any responsibility for, or makes any representation or warranty, express or implied, with
respect to the accuracy, reliability or completeness of the information contained in this presentation and none of
those parties have or assume any obligation to provide any additional information or to update this presentation. The
information in this presentation should be read in conjunction with Core’s other periodic and continuous disclosure
announcements lodged with the Australian Securities Exchange (ASX), which are available at www.asx.com.au.
To the fullest extent permitted by law, the Company, its respective affiliates and representatives, related bodies
corporate, officers, employees, partners, agents and advisers make no representation or warranty (express or implied)
as to the currency, accuracy, reliability, reasonableness or completeness of the information in this presentation and
expressly disclaims all responsibility and liability for any loss or damage arising in respect of your reliance on the
information contained in this presentation (including your reliance on the accuracy, completeness or reliability of that
information), or any errors in or omissions from this presentation, including any liability arising from negligence.
The Finniss Lithium Operation as described in this presentation as being in a state of operational readiness, and
potential investors should understand that mineral exploration, development and mining are high-risk undertakings.
There is no guarantee that the Finniss Lithium Operation can be economically exploited in the future.
This document contains statements which may be in the nature of forward-looking statements. No representation or
warranty is given, and nothing in this presentation or any other information made available by the Company or any
other party should be relied upon as a promise or representation, as to the future condition of the respective
businesses and operations of the Company.
Competent Person Statements
The Mineral Resources and Ore Reserves underpinning the production target and forecast financial information in this
announcement have been prepared by competent persons in accordance with the requirements of the JORC code.
Core confirms that it is not aware of any new information or data that materially affects the exploration results,
exploration target, mineral resource estimate and ore reserve estimate included in this announcement as cross
referenced in the body of this announcement and that all technical parameters underpinning the Mineral Resources,
Ore Reserves, production target and forecast financial information derived from the production target continue to
apply and have not materially changed. The announcement references the previously reported Mineral Resource
Estimates and Ore Reserve Estimates; “Finniss Mineral Resource Increased by 58%” on 11 April 2024, “Lithium Ore
Reserve Updated” on 25 September 2024, “Updated Finniss Lithium Operation Reserve and Resource” on 14 May 2025,
“Updated Ore Reserve at Carlton” on 10 September 2025 and “Updated Grants Mine Plan and Ore Reserve” on 10
November 2025. The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the original announcements related to previously reported
exploration results, exploration target, Mineral Resource Estimates and Ore Reserve Estimates.
Currency
Unless otherwise stated, all cashflows are in Australian dollars, are undiscounted and are in real terms (not subject to
inflation/escalation factors).
Forward‐looking Statements
Generally, this forward-looking information can be identified by the use of forward-looking terminology such as
‘outlook’, ‘anticipate’, ‘project’, ‘target’, ‘likely’,’ believe’, ’estimate’, ‘expect’, ’intend’, ’may’, ’would’, ’could’, ’should’,
’scheduled’, ’will’, ’plan’, ’forecast’, ’evolve’ and similar expressions. Persons reading this release are cautioned that such
statements are only predictions, and that the Company’s actual future results or performance may be materially
different. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that
may cause the Company’s actual results, level of activity, performance or achievements to be materially different from
those expressed or implied by such forward-looking information. Forward-looking information is developed based on
assumptions about such risks, uncertainties and other factors set out herein, including but not limited to general
business, economic, competitive, political and social uncertainties; the actual results of current exploration,
development and construction activities; conclusions of economic evaluations; changes in project parameters as plans
continue to be refined; future prices of lithium; possible variations of ore grade or recovery rates; failure of plant,
equipment or processes to operate as anticipated; accident, labour disputes and other risks of the mining industry;
and delays in obtaining governmental approvals or financing or in the completion of development or construction
activities. This list is not exhaustive of the factors that may affect forward-looking information. These and other factors
should be considered carefully, and readers should not place undue reliance on such forward-looking information.
The Company disclaims any intent or obligations to or revise any forward-looking statements whether as a result of
new information, estimates, or options, future events or results or otherwise, unless required to do so by law.
Statements regarding plans with respect to the Company’s mineral properties may contain forward-looking
statements in relation to future matters that can be only made where the Company has a reasonable basis for making
those statements.
Past Performance
Past performance information given in this presentation is given for illustrative purposes only and should not be relied
upon as (and is not) an indication of future performance.
FY26 Sustainability highlights
3
Sustainability program continues to evolve as operations ramp up
Focused on safe, reliable and sustainable operations that consider the wellbeing of our
people, the environment and the communities in which we operate
Zero recordable
injuries, zero
serious potential
incidents
LTIFR: 0.00
Targeted local
hiring initiatives
with 100%
of process plant
positions filled
locally
Total female
employee
representation
30%
Increased wet
season discharge
managed with
zero statutory
non-compliances
Greenhouse gas
emissions
inventory and
climate risk and
opportunity
assessment
underway to
support FY27 AASB
S2 disclosure
From care and maintenance to operating within 12 months
4
Core has funded, restarted and returned Finniss to production
1. Cash and available sources as at 30 September 2026. Available sources include receivables and second tranche of senior secured loan.
2. Throughput capacity uplift from brownfields plant upgrades completed in the September 2026 quarter.
3. Revenue from sale of the remaining lithium fines and concentrate stockpile in CY26, excluding first concentrate shipment as announced 25 November 2026. Refer to ASX announcement
“First Shipment of Spodumene Concentrate Post Finniss Restart” dated 25 November 2026.
FY25
Care and maintenance
TODAY
Operating
Funding Restart unfunded Fully funded A$244m1
Cash and available sources
Mining No mining or development
Mining at Grants
BP33 underground development underway
Mid CY27
BP33 first ore
Processing Plant idle Plant upgraded and producing spodumene concentrate +20%2
throughput capacity
Sales No production or sales
Stockpiled concentrate and fines sold
First concentrate shipment
A$38.5m3
stockpile sales
What we committed to and what we delivered
5
Key restart milestones delivered in ~8 months
MARCH 2026
Secure funding
A$290m strategic
funding package
secured in addition to
existing cash and sales
MAY 2026
Restart mining
Open pit mining
commenced at
Grants
JUNE 2026
Re-establish
logistics chain
Existing stockpiled
fines and concentrate
sold and shipped
JUNE 2026
Start BP33
development
Portal cut and decline
development
underway
SEPTEMBER 2026
Plant upgrades and
commissioning
+20% throughput
capacity and improved
recoveries; first
concentrate produced
NOVEMBER 2026
First concentrate
shipment
10kt of newly
produced concentrate
ready to ship
~8 months
from funding to first concentrate shipment
Finniss restarted, with a clear pathway to long life production
6
Existing plant fed by open pit now, underground next, with growth options nearby
1. Refer to ASX announcement "FID Approved and Funding Secured for Finniss Restart" dated 18 March 2026 for further information.
2. The Carlton Ore Reserve (ORE) of 4.5Mt @ 1.19% Li2O is comprised of 1.7Mt @ 1.19% Li2O Proved ORE and 2.8Mt @ 1.19% Li2O Probable ORE.
3. Exploration results: Refer to ASX announcement "Thick High-Grade Lithium Intersections at Blackbeard" dated 19 October 2026 and “High-Grade Lithium Intersection Extended at
Blackbeard” dated 6 November 2026. The Company confirms it is not aware of any new information or data that materially affects the information included in that announcement.
4. Approximate straight-line distance from the processing plant.
1
3
2
4
All four assets within ~20km of the existing processing plant4
1 Grants Open Pit
NOW
MINING
134kt SC5
1
~5 month mine life remaining | Balance of
unmined Ore Reserve will remain available for
potential underground mine
Provides near term cashflow before BP33
becomes the long-term production base
2 BP33 Underground
NEXT
DEVELOPMENT
1.2Mtpa ore · 257ktpa SC5
1
10+ year mine life and open at depth; first ore
mid CY27
Drilling underway targeting resource extension
3 Carlton Deposit
GROWTH
ORE RESERVE
4.5Mt Ore Reserve
2
4 Blackbeard Prospect 3
UPSIDE
DRILLING
92m @ 1.25% Li₂O
74m @ 1.32% Li₂O
Maiden resource targeted FY27
Studies underway
BP33 supports low cost, long term production
7
US$533/t unit cost provides resilience through lithium price cycles
1. Refer to ASX announcement "FID Approved and Funding Secured for Finniss Restart" dated 18 March 2026 for further information.
2. Nameplate production. Equivalent to 257ktpa of SC5 concentrate (5.0% Li₂O equivalent basis).
3. Unit cost calculated at SC6 FOB, ex-royalties. Represents steady state unit costs during the period where BP33 is at full capacity. Based on the exchange rate of AUD/USD 0.70.
4. SC6 price: Fastmarkets, Spodumene min 6% Li₂O, CIF China, US$/t, monthly average.
SC6 PRICE VS BP33 UNIT COST (US$/t)1,4
US$533/t
SC6 EQ. UNIT COST3
A$762/t; steady state at full capacity
48%
EBITDA MARGIN1
At US$1,500/t SC6 (FID case)
10+ years
MINE LIFE1
1.2Mtpa
THROUGHPUT1
214ktpa
SC6 EQ. PRODUCTION2
78%
GLOBAL RECOVERIES1
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
2022 2023 2024 2025 2026
Unit Cost ~US$533/t
3
(A$762/t
1
)
SC6 Price4
Unit cost
533
US$/t
BP33: first development ore mid CY27, steady state from mid CY28
8
Underground development and surface construction under way, with a 12-month ramp-up to steady state from first ore
Underground
development
Surface
infrastructure
construction
Production
Exploration
MARCH CY26
FID TODAY MID CY27 MID CY28 BEYOND
Decline development
Portal cut
Construction – Ventilation and cooling | Paste plant
Box cut remediation
Ramp-up
12 months
Steady state
10+ year mine life
First ore, mid CY27
Drilling program
Potential resource
extension
Funding supports execution through current market conditions
9
Grants cash flow is upside, not a funding requirement
1. Cash, receivables and undrawn senior secured loan (tranche 2) as at 30 September 2026.
2. Refer to the Company's ASX announcements titled "Finniss Funding and Restart Presentation" and "FID Approved and Funding Secured for Finniss Restart", both dated 18 March 2026.
3. Potential cash flows from Grants are illustrative only and do not constitute guidance. Actual cash flows will depend on realised spodumene prices, production and sales volumes, product grade,
operating performance, costs and other applicable commercial terms.
FUNDING POSITION AT 30 SEPTEMBER 2026 (A$m)
200
35
157
87
Available sources¹ Remaining restart
capital²
Liquidity buffer
Cash
Receivables
Undrawn debt
A$244m
Available sources1
Cash A$200m, receivables A$9m and undrawn
debt A$35m
A$157m Remaining restart capital2
Fully funded without relying on Grants cash flow
A$87m
Liquidity buffer
Protects the BP33 development plan through
current market conditions
↑ Plus: Grants cash flow3
Potential additional liquidity, not relied on for restart funding
244
Growth beyond 1.2Mtpa leveraging existing infrastructure
10
Existing infrastructure means the next step is a second ore source, not a second plant
1. The expansion case remains conceptual and is contingent on future drilling results at Blackbeard and study outcomes at Carlton, which are required to further assess the scale and
economic potential of the opportunities.
EXISTING
Infrastructure
Crusher 2.4Mtpa
capacity above BP33’s
1.2Mtpa requirement
Ample port capacity
Scalable logistics
chain
+
UPGRADE
DMS plant
upgrades
Requires plant
upgrades to lift
throughput above
1.2Mtpa +
DEVELOP
A second ore source
Carlton
Status: Reserve
4.5Mt Ore Reserve or
Blackbeard
Status: Drilling
Thick, high-grade
intercepts
Targeting maiden
resource FY27
Drilling and studies will determine the preferred
option, timing and capital requirements
POTENTIAL OPPORTUNITY
Expanding
existing
infrastructure
provides a
pathway to
increase
production above
1.2Mtpa
1
STUDIES UNDERWAY
What’s coming next?
11
Key milestones over the next 18 months
Timing is indicative and subject to the risks and assumptions set out in the Important and Cautionary Notes. CY = calendar year; FY = financial year ending 30 June.
H1 CY27
1
Reflux classifier
installation
Further improves
recoveries
H1 CY27
2
Blackbeard
potential maiden
Mineral Resource
Targeted from drilling
of thick, high-grade
intercepts
MID CY27
3
BP33 first ore
Decline reaches the
orebody; first
development ore to
the plant
MID CY27
4
Expansion study
outcomes
Preferred pathway to
lift ore feed above
1.2Mtpa
H2 CY27
5
BP33 surface
infrastructure
complete
Ventilation, cooling
and paste plant
commissioned
MID CY28
6
BP33 steady state
1.2Mtpa ore; ~257ktpa
SC5 equivalent
Operating.
Mining, producing and shipping
Funded.
Through to BP33 production
Resilient.
Positioned to operate through cycles
Growth.
Beyond 1.2Mtpa
WHY CXO?
corelithium.com.au
Contact
Core Lithium Ltd
Level 4, 186 St Georges Terrace
Perth WA 6000
E info@corelithium.com.au
Investor Enquiries
Paul Brown
Managing Director
+61 8 8317 1700
Media Enquiries
Cameron Morse
FTI Consulting
+61 433 886 871
This presentation has been approved for release
by the Core Lithium Board