FID Approved and Funding Secured for Finniss Restart
Released
Released
Announcement PDF
Level 4, 186 St George’s Terrace T 61 8 8317 1700 ABN 80 146 287 809
Perth WA 6000 E info@corelithium.com.au ASX CXO
corelithium.com.au
1
18 March 2026
ASX: CXO Announcement
Not for release to US wire services or distribution in the United States
Final Investment Decision and Funding Secured
for the Restart of the Finniss Lithium Operation
Highlights
• Final Investment Decision (FID) approved by the Core Board for the restart of operations
at the Finniss Lithium Project (Finniss or the Project).
• Fully funded restart package includes strategic support (Strategic Funding) of US$120
million (A$170 million1) in aggregate from a consortium comprising of Glencore Australia
Holdings Pty Limited (Glencore), InfraVia CMF Invest S.à r.l. (InfraVia) and Nebari
Natural Resources Credit Fund II, LP (Nebari) (together Strategic Partners), and an
intended A$120 million (before costs) equity raise.
• In conjunction with the Strategic Funding, Core has entered into a purchase and
distribution arrangement with Glencore International AG (Marketing Arrangement),
leveraging their global platform whilst retaining full flexibility to place offtake.
• Project delivers compelling economics, with a pre‑tax NPV8 of A$1.1 billion2,3, and free
cash flow generation of A$1.7 billion, underpinned by competitive unit operating costs of
A$762/t4 and a conservative long‑term spodumene concentrate price assumption of
US$1,500/t1 CIF (current spot price is ~US$2,200/t CIF).
• The restart repositions Finniss as a lower cost, long-life, brownfield lithium operation with
a shorter path to nameplate production of 214ktpa2, reduced execution complexity and
untapped expansion and exploration upside potential.
• Key mining, processing and services contracts have been advanced through competitive
tendering, providing pricing confidence and a clear execution pathway for the Finniss
restart.
• Early works and site preparation to commence immediately, with the Grants open pit
mining and processing restart followed by BP33 underground development, providing a
staged ramp‑up profile.
1. Based on exchange rate of AUD/USD $0.7074.
2. Based on 6% spodumene concentrate price of US$1,500/t CIF and an exchange rate of AUD/USD 0.7000.
3. Refer to section below and references to prior announcements included in this section.
4. Represents Unit operating cost during the period where BP33 is at full capacity (~1.2Mtpa). Unit operating cost (FOB excluding royalties) includes
mining, processing, haulage, port charges, and site based general and administration costs. It is calculated on an SC6 equivalent basis.
2
corelithium.com.au
Core Lithium Ltd (ASX: CXO) (Core or the Company) is pleased to announce it has secured a comprehensive
funding package (the Funding Package) to fully fund the construction and restart of Finniss, and that the Core
board of directors (Board) has formally approved the Final Investment Decision (FID) to restart operations at
Finniss in the Northern Territory.
This decision represents a significant milestone for the Company, following extensive technical work, engagement
with strategic partners over the past year and a strengthened lithium market outlook.
The FID follows completion of a comprehensive restart plan, updated mine planning, Front-End Engineering and
Design work, and refined operating strategies to reposition Finniss as a lower‑cost, long‑life lithium operation.
Core’s Board approval reflects the improved economic metrics of the restart, as well as the Company’s confidence
in delivering sustained production supported by a de-risked execution plan.
In conjunction with approving the FID, Core has secured a fully committed funding package that provides certainty,
flexibility and long-term alignment with strategic partners. This integrated funding structure enables immediate
mobilisation and commencement of pre‑production capital deployment, including mining contractor engagement,
site preparations, plant optimisation works and underground development activities.
The Funding Package comprises a US$70 million (A$99 million1) Convertible Note from Glencore and InfraVia
(Convertible Note), a US$50 million (A$71 million1) senior secured debt facility from Nebari (Senior Secured
Loan) and an intended A$120 million (before costs) equity raising. Together, these funding sources, along with
Core’s forecasted cash reserves of A$41 million (as at 31 March 2026) and the A$11 million proceeds from recent
spodumene concentrate sale5, fully support the restart and provide liquidity during ramp-up as Finniss transitions
toward steady-state operations.
Core’s Strategic Partners bring deep expertise across marketing, project execution, mining operations and
environmental, social and governance. Their long-term support provides Core with enhanced execution capability,
strengthened commercial flexibility and access to premium global sales channels. These partnerships underpin
the Company’s confidence in delivering a successful restart and operational performance.
Cautionary Statement
The FID outcomes include the Grants, BP33, and Carlton deposits, to produce a mine plan and resultant financial
evaluation, including the Measured, Indicated, and Inferred Mineral Resources. The Grants, BP33 and Carlton
Measured and Indicated quantities are considered to be at least to a PFS level of accuracy as defined by the
2012 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC
Code).
There is a low level of geological confidence associated with inferred mineral resources and there is no certainty
that further exploration work will result in the determination of indicated mineral resources or that the production
target itself will be realised.
The FID outcomes contain approximately 13% of Inferred Mineral Resources. An Inferred Mineral Resource has
a lower level of confidence than an Ore Reserve or a Measured and Indicated Mineral Resource and there is no
certainty that further exploration work will result in the conversion of the Inferred mineralisation into an Ore
Reserve or Measured or Indicated Mineral Resource or that the production target itself will be realised.
Refer to the Company's ASX announcements titled “Updated Finniss Lithium Project Ore Reserve and Mineral
Resources Estimate” dated 14 May 2025, “Restart Study Repositions Finniss Operations” dated 14 May 2025,
“Updated Ore Reserve at Carlton” dated 10 September 2025 and “Updated Grants Mine Plan and Ore Reserve”
dated 10 November 2025 for full details of the updated Finniss Ore Reserve, including a Competent Person
statement. Please also refer to the section below titled “Finniss Lithium Project Update” for the key outcomes in
respect of the technical and economic assumptions for Finniss and no material change confirmations in respect
to certain aspects of the Restart Study (defined below), together with the “Important Information and forward-
looking statements” disclosure at the end of this announcement.
5. Refer to ASX Announcement “Sale of Spodumene Concentrate Stockpile” on 26 February 2026.
3
corelithium.com.au
Core’s Managing Director Paul Brown said:
“Today’s approval of the Final Investment Decision and the securing of a fully committed Funding Package is the
culmination of 18 months of diligent planning and execution for Core. The restart plan delivers a de-risked, lower
cost, long-life operation with robust economics supported by valued Strategic Partners who share our long-term
vision for Finniss.
The transaction with Glencore, InfraVia and Nebari is the culmination of a rigorous and highly competitive
nine‑month strategic funding process. Securing such high‑calibre partners reflects the strength of that process.
The resulting funding package positions us to deliver sustainable returns while minimising dilution for the
long‑standing shareholders who have consistently supported us.
With all major approvals in place and a proven processing plant ready for restart, Core will now progress
mobilisation activities. Near‑term ore feed will be sourced from the Grants Open Pit, providing a low‑risk and rapid
pathway to recommencement of concentrate production. BP33 underground development will occur in parallel,
supporting a transition to long‑life, high‑margin underground operations.
The Company remains focused on safe, disciplined execution as it advances a staged restart program through
2026 and 2027 with first spodumene concentrate production targeted for the September quarter 2026. First ore
from Grants is targeted within one month of contractor mobilisation, with BP33 first ore expected in mid‑CY2027
and ramp‑up to nameplate production of 1.2Mtpa in mid‑2028.
Employment levels at Finniss are expected to scale across construction and operations, supporting a material
number of jobs over the project lifecycle. Core appreciates the support Finniss has received from the Northern
Territory government and local stakeholders.”
Glencore’s Head of Lithium Robin Francois said:
“Glencore is one of Australia’s largest producers and marketers of critical and strategic minerals. We are pleased
to play an important role in this transaction which supports the restart of Finniss Lithium Operation in the Northern
Territory and brings significant economic benefits to the entire region.
We share the Government’s view that this operation is vital to the regions’ critical minerals strategy and is a key
asset for achieving the Northern Territory Government’s ambition of a A$40 billion economy by 2030.
This is another example of how Glencore’s unique marketing business can support Australian mining companies
while we continue to expand as a leading supplier of critical minerals.”
InfraVia’s Founder and CEO Vincent Levita said:
“We are delighted to become a strategic funding partner of Core to support the upcoming operation of the Finniss
lithium project. Combining strong technical fundamentals with a highly experienced team, we believe this project
offers significant operational and strategic potential.
Lithium is a critical component of the global energy transition, and investing in reliable sources of supply is
essential to the development of resilient battery and electric vehicle supply chains. This investment is fully aligned
with the strategy of our Critical Metals fund.”
Nebari Senior Managing Director Roderik van Losenoord said:
“We are pleased to partner with Core to progress the Finniss mine back into production. We commend the Core
team for their focus on developing a sound technical and financial basis that will achieve this restart.
We thank management for their trust in Nebari, and we look forward to supporting Core as they realise Finniss’
significant potential.”
4
corelithium.com.au
Funding Package
Core has secured funding for the restart with a fully funded restart solution secured through a diversified financing
package. The funding package provides certainty, flexibility and alignment with long term strategic partners.
The package comprises:
• US$70 million (A$99 million1) Convertible Note;
• US$50 million (A$71 million1) Senior Secured Loan; and
• An intended A$120 million (before costs) equity raising, including an unconditional placement of
approximately 254 million New Shares to raise approximately A$53 million (before costs). (Unconditional
Placement) and conditional placement of approximately 317 million New Shares to raise approximately
A$67 million (before costs), subject to shareholder approval (Conditional Placement), in each case to
institutional and sophisticated investors.
The overall Funding Package has been designed to provide certainty, flexibility and alignment with Core’s long-
term Strategic Partners, in the least dilutionary manner, whilst maintaining an attractive cost of capital, to ensure
existing shareholders are able to participate in the future growth potential of the Company.
The security package for the Convertible Notes and Senior Secured Loan will cover all assets. Certain 'excluded
assets' relating to non-lithium product and rights will be subject to security on a featherweight basis only. The
security documents have been signed on the same date as the Convertible Note Deeds and Senior Secured Loan
Agreement and will take effect following FIRB approval
Convertible Notes
The US$70 million (A$99 million1) of Convertible Notes to be issued to InfraVia and Glencore provide a source of
long‑dated, flexible capital. The Convertible Notes have been structured in two tranches as follows:
• The US$26 million upfront component (Tranche 1 Notes), being issued to InfraVia, will be issued after
the Unconditional Placement closes and within 15 business days after satisfaction of certain conditions
(including closing an equity raise of US$25 million, that will be satisfied upon closing the Unconditional
Placement) and provides immediate funding support; and
• The deferred component of US$44 million delivered following the Conditional Placement and remains
subject to shareholder approval and Foreign Investment Review Board (FIRB) Approval.
The Tranche 1 Notes will be issued utilising Core’s existing ASX Listing Rule 7.1 placement capacity utilising
approximately 145 million securities.
The coupon of 8.00% in the Convertible Notes is linked to the achievement of steady‑state production at BP33
(10% coupon prior), and provides a clear incentive structure tied to operational performance. In addition, the
Convertible Notes include a sustainability‑linked mechanism offering incremental reductions to the coupon upon
delivery of agreed key performance indicators (KPI).
Conversion of the Convertible Notes to equity occurs at 120% of the Equity Raise price of A$0.21 per share
(subject to the customary adjustments) (Conversion Price) with a 6‑year maturity from the issue date of Tranche
1 Notes. Noteholders may convert their Convertible Notes at any time up to five business days prior to maturity.
Early redemption rights are available to Core at the earlier of achieving of steady-state production at BP33 or after
3-years (subject to the satisfaction of a share price VWAP condition), providing a clear pathway for the Company
to manage or retire the Convertible Notes ahead of maturity should market conditions be favourable.
Additional rights include customary governance features, establishment of a technical steering committee and
ability for InfraVia to appoint one board observer if it holds Convertible Notes or has voting power greater than 5%
(subject to requisite approvals), the ability for InfraVia to appoint one non-executive director if InfraVia's voting
power exceeds 10% (subject to requisite approvals) ) and the equity-linked offtake option granted to InfraVia to
purchase lithium spodumene concentrate from Finniss at market-linked pricing. Detailed terms are set out in the
Appendix to this announcement.
Senior Loan
The US$50 million (A$71 million1) Senior Secured Loan provides a flexible funding structure to support the
Company’s operational and strategic requirements. The facility is structured in two tranches:
• Tranche 1: a US$25 million facility to be drawn at the first drawdown, providing immediate liquidity; and
5
corelithium.com.au
• Tranche 2: a US$25 million undrawn facility at closing that can be accessed at the Company’s election no
earlier than three months following the drawdown of Tranche 1.
This staged approach enables Core to optimise capital utilisation and maintain financial flexibility during project
ramp-up.
Each tranche benefits from a deferred amortisation profile, with principal repayments commencing 18 months
after the closing date and amortising at 3.5% per month until maturity. The facility matures 48 months from the
closing date, supporting both near‑term activities and medium‑term development plans.
The interest rate is set at the Secured Overnight Finance Rate (“SOFR”) plus 5.0% per annum6 (inclusive of a
3.5% SOFR floor). The Company may elect to capitalise interest up to nine months from the closing date, offering
additional balance sheet flexibility during the initial ramp-up period.
The Senior Secured Loan is inter-conditional to the Tranche 2 Notes and therefore remains subject to shareholder
approval and FIRB Approval.
Further detail on the terms including covenants, distribution restrictions, and conditions precedent, are provided
in the Appendix to this announcement.
Equity Raising
Details of the Placement
The non-underwritten Placement of approximately 571 million of new fully paid ordinary shares (New Shares) will
be conducted in two tranches:
• Unconditional Placement: 254 million New Shares to raise approximately A$53 million (before costs).
Tranche 1 will be conducted under Core’s existing ASX Listing Rule 7.1 placement capacity. Settlement of
Tranche 1 is expected to occur on 23 March 2026; and
• Conditional Placement: 317 million New Shares to raise approximately A$67 million (before costs), subject
to shareholder approval at a General Meeting (GM) expected to be held in late April 2026. Settlement of the
Conditional Placement will occur shortly after shareholder approval is obtained, (together, the Equity
Raising or Placement)
The Offer Price for the Placement is A$0.21 per New Share, representing a 4.5% discount to the last traded price
on ASX of A$0.22 per share.
Certain Directors of Core have indicated their intention to participate in the Placement, subject to obtaining the
requisite shareholder approvals at the same EGM at which approval for the Conditional Placement will be sought.
Any Director participation will be on the same terms and at the same Offer Price as other investors under the
Placement.
New Shares issued under the Unconditional, and Conditional Placement (including any New Shares issued to the
Core Directors under the Placement) will rank equally (pari passu) with existing fully paid ordinary shares of Core.
Further details of the Offer are set out in the Company’s investor presentation lodged with ASX today. The investor
presentation includes key information such as the sources and uses of funds, key risks associated with an
investment in Core, and foreign selling restrictions applicable to the Placement.
Marketing Arrangement
As part of the Strategic Funding, Core has entered into a Marketing Arrangement with Glencore for the sale of
lithium product from Finniss. Under the agreement, Glencore will market and sell all spodumene concentrate and
lithium bearing direct shipment ore produced by Core at Finniss, with a joint marketing and shipping strategy. Core
retains full flexibility to place offtake and refer customers directly to Glencore.
The agreement has a 5‑year term and includes flexible arrangements for shipping, planning and customer
referrals, providing a structured and transparent marketing framework to market Core’s product.
6. Inclusive of a 3.5% SOFR floor.
6
corelithium.com.au
Key dates
The indicative timetable for the Equity Raising is set out below:
Event Time (Australian Eastern Daylight Time) / Date
Trading halt on ASX Wednesday, 18 March 2026
Announcement of Placement Wednesday, 18 March 2026
Placement Bookbuild Wednesday, 18 March 2026
Announcement of the completion of the
Unconditional Placement
Thursday, 19 March 2026
Trading halt lifted on ASX Thursday, 19 March 2026
Settlement of New Shares issued under the
Unconditional Placement
Monday, 23 March 2026
Allotment and normal trading of New Shares issued
under the Unconditional Placement
Tuesday, 24 March 2026
Despatch of Notice of Meeting Late March
General Meeting (Notice of Meeting + 28 Days) Late April
Settlement of New Shares under the Conditional
Placement
Late April/Early May
Allotment and normal trading of New Shares issued
under the Conditional Placement
Late April/Early May
The Placement timetable is indicative only and subject to variation. The Company reserves the right to alter the timetable at its discretion and
without notice, subject to the ASX Listing Rules, the Corporations Act and other applicable law.
Use of Proceeds
Proceeds from the Funding Package will primarily support the restart of the Finniss Project. This includes
approximately A$208 million of restart capital covering Grants pre‑production works, BP33 underground
infrastructure and targeted plant and site upgrades. A further A$69 million will be used to cover Finniss working
capital, transaction costs and working capital to support restart activities, commissioning and early operations. In
addition, A$30 million has been allocated to near‑term growth initiatives and exploration programs, including
drilling and study work for the Blackbeard prospect to progress future resource and project expansion
opportunities.
Use of Proceeds A$ million1
Restart capital with contingency 208
Working capital, transaction costs and general corporate purposes 69
Growth and exploration 30
Total Use of Proceeds2
307
Notes:
1. Based on exchange rate of AUD/USD $0.7000.
2. The above is a statement of current intentions of Core as at the date of this announcement. Due to market conditions and/or any number of other
factors, actual expenditure may differ significantly to the above estimates. As with any budget, intervening events (including exploration success or
failure) and new circumstances have the potential to affect the way funds are ultimately applied. Core reserves their right to alter the way funds are
applied on this basis.
7
corelithium.com.au
Finniss Lithium Project update
Operation overview
Finniss is located on the Cox Peninsula in the Northern Territory, ~25km south of Darwin and 88km by road to
Darwin Port. The Project comprises two adjacent mine sites, the Grants Lithium Project and the BP33
Underground Mine.
Core will recommence open-pit mining at Grants and commence underground development for BP33 in the June
quarter 2026, with ore processed at the existing Grants processing facility. The consolidated Life of Mine (LOM)
plan also considers potential future underground mining at Grants and the development of the Carlton
Underground Mine, resulting in a 20-year LOM.
Key Outcomes
Since completing the Finniss Restart Study (Restart Study) in May 2025, the Company has updated mine
planning, undertaken Front-End Engineering and Design work and refined its operating strategies for FID. Project
economics have also been updated using a base case SC6 spodumene concentrate price of US$1,500/t CIF,
compared to the long-term US$1,330/t CIF in the May 2025 Restart Study, reflecting a significant improvement in
market pricing, which is currently approximately US$2,200/t CIF.
The Company has refined the comprehensive, bottom-up assessment of the Project. The focus has been on
updating the mining and processing plan based on the additional technical work that has been completed, which
includes:
• Open Pit plan for Grants with updated mining schedules;
• An enhanced process flowsheet and proposed process plant upgrades;
• Detailed operating and capital cost estimates;
• Future upside opportunities; and
• Updates to Ore Reserves for Grants, BP33 and Carlton
The FID decision focuses on optimising the on-site infrastructure. Other than the comments noted in this
announcement, the remaining technical and economic assumptions of Finniss remain unchanged relative to the
Restart Study (released to the ASX on 14 May 2025) and the Updated Grants Mine Plan and Ore Reserve
(released to the ASX on 10 November 2025). The Mineral Resource Estimate and Ore Reserve (other than for
the Grants deposit) remain unchanged from the 30 April 2025 estimate (released to the ASX on 14 May 2025).
The Grants Ore Reserve was updated and released to the ASX on 10 November 2025.
The Company confirms that there have been no material changes since completion of the Restart Study to the
project location, property description, land tenure and access, accessibility, climate and local resources,
production history, geological setting and deposit context, existing infrastructure and approvals, tailings storage,
site-to-port logistics, power supply, water supply, flood risk, environmental and regulatory approvals, or royalties.
8
corelithium.com.au
Table 1: FID outcomes summary
Key Metrics Units Amount
Life of Mine (LOM) Years 20
Annual production throughput Mtpa 1.2
Ore processed (Ore Reserves)7 Mt 15.6
Ore processed (feed total) 7 Mt 17.9
Average feed grade % 1.27
Global recovery % 78
Nameplate annual concentrate produced (SC6 eq.) ktpa 214
Concentrate produced (SC6 eq.)7 kt 2,870
Operating Costs
Mining A$/t mined 78
Processing & tailings A$/t processed 40
Site General & Administration A$/t processed 7
Transport A$/t product 36
Unit operating Costs (SC6 eq. excluding
royalties)8
A$/t 762
Capital Costs
Restart Capital A$M 208
Sustaining Capital8 $/t mined 21
Financial metrics
Free cash flow generation A$M 1,700
EBITDA Margin % 48%
NPV8 Pre-tax A$M 1,104
NPV8 Post-tax A$M 837
Payback Period years 3
IRR Unlevered Post-tax % 76.5%
7. Refer to Table 3 for a breakdown of the relevant proportions of Probable Ore Reserves, Proved Ore Reserves, and Inferred Mineral Resources
underpinning the production target.
8. Calculated at a nameplate mine production.
9
corelithium.com.au
Mining
BP33 contributes 88% of ore feed in the first ten years of operation. Mineralisation at BP33 is hosted within a
large, sub-vertical pegmatite body. The BP33 pegmatite is 290m in strike length and up to 30m in true width.
There is a very strong steep southerly plunge component with a depth extent currently more than 800m. These
characteristics make BP33 well suited for highly productive, low cost, Long Hole Open Stoping mining methods.
Dual access to the ore body from the decline will allow flexibility in stope sequencing.
Table 2: Statement of Ore Reserves9
Deposit Classification
Quantity
(Mt)
Li2O
(%)
Contained
Li2O
(kt)
BP33 Underground
Proved 2.6 1.27 32
Probable 6.7 1.32 89
Grants Open Pit and
Underground
Proved 1.2 1.43 17
Probable 0.4 1.41 5
Carlton Underground
Proved 1.7 1.19 20
Probable 2.8 1.19 34
TSF/Stockpiles
Proved - - -
Probable 0.3 0.68 2
Total
Proved 5.4 1.28 69
Probable 10.2 1.27 129
Total 15.6 1.27 198
9. Refer to the Company ASX announcement titled "Updated Grants Mine Plan and Ore Reserve" dated 10 November 2025 for further information
regarding the Ore Reserve.
10
corelithium.com.au
Approximately 32% of the total Finniss Mineral Resources have been included in the Ore Reserve, presenting
significant scope for extensions to the mine life in future with further drilling and mining studies.
The FID production profile supporting the Final Investment Decision is predominantly based on Ore Reserves,
with Inferred Resources representing approximately 13% of total scheduled material and occurring later in the
mine plan. Inferred material does not underpin near-term production or the economic outcomes used to support
the FID.
Table 3: FID Production Profile10
Mine
Centre LOM
Grants
Proved
Ore (Mt) 1.2
Li2O (%) 1.43
Probable
Ore (Mt) 0.4
Li2O (%) 1.41
BP33
Proved
Ore (Mt) 2.6
Li2O (%) 1.27
Probable
Ore (Mt) 6.7
Li2O (%) 1.32
Inferred
Ore (Mt) 0.7
Li2O (%) 1.31
Total
Ore (Mt) 10.1
Li2O (%) 1.31
Carlton
Proved
Ore (Mt) 1.7
Li2O (%) 1.19
Probable
Ore (Mt) 2.8
Li2O (%) 1.19
Inferred
Ore (Mt) 1.4
Li2O (%) 1.19
Total
Ore (Mt) 5.9
Li2O (%) 1.19
Total Mined
Ore (kt) 17.6
Li2O (%) 1.28
Processing
Feed
Mt 17.9
Li2O (%) 1.3
Li2O (kt) 227.4
LOM Recovery (%) 78
SC6eq (Mt) 2.9
10. Table details the proportions of probable ore reserves, proved ore reserves and inferred mineral resources underpinning the production target.
11
corelithium.com.au
Table 4: Statement of Mineral Resources11
Resource Category Tonnes (Mt) Li2O (%) Contained Li2O (kt)
Measured 6.3 1.41 89
Indicated 21.9 1.29 283
Inferred 20.3 1.18 239
Total 48.5 1.26 610
Processing
No fundamental changes have been made to the operating structure or processing flowsheet underpinning the
Restart Study. Rather, the existing operating model has been reaffirmed through further detailed engineering and
technical review, which has validated the capital inputs and execution assumptions adopted in the Restart Study.
This additional work has increased confidence in the accuracy and robustness of the capital estimates, while
confirming that the proposed processing configuration remains the most efficient, lower-risk and value-accretive
pathway for restarting operations at Finniss.
Capital and Funding
Restart capital of A$208 million has been identified to support a positive FID, fully underwriting first production,
ramp-up readiness and early operations with appropriate contingency. It largely comprises $184 million for BP33
underground infrastructure, with a further $18 million allocated for plant and site infrastructure upgrades, and $6
million for Grants open pit site establishment costs. The restart capital requirement is fully funded through a
diversified financing package, as detailed above.
Operating Costs
The operating cost model for FID has been fully updated using revised mine schedules, confirmed contractor
tender rates and the refined processing flowsheet. Mining cost of A$78/t mined is defined by tendered and refined
mining and physical parameters. The acquisition of, crushing infrastructure, along with enhanced flow sheet and
increased throughput will reduce processing costs to A$40/t processed which is consistent with the lower end of
the Restart Study range.
Table 5: Operating Cost Summary
Cost Centre Units Total
Mining A$/t mined 78
Processing & Tailings A$/t processed 40
General & Administration A$/t processed 7
Transport A$/t product 36
Unit operating Cost (SC6 eq. excluding royalties)* A$/t 762
*Unit operating cost (FOB excluding royalties) includes mining, processing, haulage, port charges, and site based
general and administration costs. It is calculated on an SC6 equivalent basis.
11. Refer to the Company's ASX announcements titled “Finniss Mineral Resource Increased by 58%” dated 11 April 2024, “Updated “Updated Finniss
Lithium Project Ore Reserve and Mine