Core Lithium 2024 Annual Report to Shareholders
Released
Released
Announcement PDF
ASX: CXO
Annual Report
2024
Core Lithium | 2024 Annual Report
About this Report
Core Lithium Ltd is the 100% owner of the Finniss Lithium
Operation – the Northern Territory’s first lithium mine, and
Australia’s only lithium mine outside of Western Australia. Finniss
is located just 88km by sealed road to the Port of Darwin and
supported by one of the best logistics chains of any Australian
lithium project. The operation is currently on hold while restart
studies are completed and lithium market conditions stabilise.
Contents
The Year in Review
2
Finniss Milestone Timeline
4
Restart Ready
6
Chair’s Letter
8
Chief Executive Officer’s Report
10
Operating and Financial Review
12
Sustainability
31
Tenement Schedule
40
Mineral Resource and Ore Reserves Statement
41
Directors’ Report
46
Auditor’s Independence Declaration
68
Financial Report
69
Independent Auditor’s Report
109
ASX Additional Information
112
Corporate Information
114
Important Information
Acknowledgement of country
This Annual Report covers Core
Lithium Ltd (“Core”, the “Parent” or
the “Company”) and its subsidiaries,
collectively referred to as “the Group”.
The financial report is presented in
Australian dollars. Core is a company
limited by shares, incorporated and
domiciled in Australia.
Core acknowledges First Nations
people, the traditional custodians of
the land on which we work throughout
Australia. We pay our respects to
the people and cultures, and to their
elders past, present and emerging.
We recognise their connection to land,
water and community, and their rich
contribution to society.
The Company’s registered office and
principal place of business is:
Core Lithium Ltd
Level 9, 2 Mill Street
Perth 6000
Western Australia
1
The Finniss Lithium
Operation has extensive
infrastructure in place
including a 1 million tonne
per annum processing plant
and a full logistics chain
from mine to port.
2
Core Lithium | 2024 Annual Report
The Year in Review
Mining operations were
paused in January 2024 and
processing of stockpiles was
completed in June 2024
Operations
Read more pages 12–13
Sales and marketing
Read more page 14
95,020dmt 97,423dmt
Projects and exploration
Read more pages 15–20
~500km2
spodumene concentrate
produced
spodumene concentrate sales
landholding in the Bynoe
pegmatite field
Record monthly recovery
rate of 65% in May 2024
First lithium fines shipment
made in September 2023
Finniss Global Mineral Resource
increased to
Cash operating costs of
$1,396/dmt
48.2Mt 1
66,140wmt
@1.26% Li2O
5,178wmt of concentrate
and up to 75,000wmt of
fines available for sale
cash spent on
exploration in FY24
lithium fines sales
$26.6m
1. Refer to “Finniss Mineral Resource Increased
by 58%” as released on 11 April 2024. Core
Lithium confirms that the Company is not aware
of any new information or data that materially
affects the Mineral Resource Estimates cross
referenced in this report and confirms that all
material assumptions and technical parameters
underpinning the estimates continue to apply
and have not materially changed.
3
Restart study to be
completed in FY25
Maintaining the operations
in a restart ready state
Complying with all
licence requirements
Bottom-up assessment
of cost base
Review of operating model
4
Core Lithium | 2024 Annual Report
Finniss Milestone Timeline
A Rapid Pathway to Production
2020
2019
2018
2017
• BP33 MRE
grows 50%
• BP33 emerges
as high-priority
target
• Finniss discovery
• Bynoe
landholding
increased
• Maiden MRE
at Grants
• Grants mining
lease lodged
• Maiden MRE
at BP33
• Scoping study
• Grants Mining
Lease granted
• Finniss DFS
• AAPA
Certificate
granted
• EPA assessment
completed
• Grants MMP
submitted
• Yahua offtake
agreement
• BP33 approvals
commence
• Grants MMP
approved
• Finniss awarded
Major Project
status
• Grants Mining
Lease granted
• Darwin Port
agreement
5
Finniss Mineral
Resource Estimate
grows
BP33 grows
Finniss MRE grows
10.1Mt
18.9Mt
30.6Mt
@1.48% Li2O2
@1.31% Li2O
@1.32% Li2O1
Finniss Ore
Reserve grows
10.6Mt
2024
@1.3% Li2O
2023
2022
2021
• Updated DFS
• Ganfeng offtake
$125M raising
• Final Investment
Decision
• Construction
commences
• Core joins ASX200
• Finniss ORE grows to
10.6Mt @1.3% Li2O
• Strategic review
undertaken following
lithium price fall
• BP33 mine
authorisation and
MMP approved
• Finniss officially
opened
• $50M early works
approved
• Crushing plant
commissioned
• $111.4M institutional
placement and Share
Purchase Plan
• Maiden DSO sale
• Construction
complete
• First concentrate
produced
• BP33 Early works
commence
• Mining of Grants pit
suspended
• Processing
operations paused
• BP33 boxcut
suspended
• Restart studies
commenced
• Review of regional
exploration targets
• First delivery into
long-term offtakes
• Additional offtakes
• $100M institutional
placement
• Mining commences
1. Refer “Significant Increase to Finniss Resources and Reserves” released on 12 July 2022. Total Mineral Resource Estimate (MRE) of 18.9Mt @ 1.32% Li2O is
comprised of Measured MRE of 5.60Mt @ 1.46% Li2O, Indicated MRE of 7.69Mt @ 1.35% Li2O and Inferred MRE of 5.57Mt @ 1.12% Li2O.
2. Refer “BP33 Mineral Resource more than Doubled” released on 6 March 2023. Total MRE of 10.1Mt @ 1.48% Li2O is comprised of Measured MRE of
2.85Mt @ 1.46% Li2O, Indicated MRE of 4.09Mt @ 1.53% Li2O and Inferred MRE of 3.17Mt @ 1.45% Li2O.
Core Lithium confirms that the Company is not aware of any new information or data that materially affects the Mineral Resource Estimates and Ore Reserve
Estimates and exploration results cross referenced in this report and confirms that all material assumptions and technical parameters underpinning
the estimates continue to apply and have not materially changed. Core confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the original announcements.
6
Core Lithium | 2024 Annual Report
Restart Ready
The Finniss Lithium Operation is a highly valuable
and strategic asset as the only lithium operation
in Australia outside of Western Australia.
Finniss has a modern, high quality process plant and associated
infrastructure and a proven logistics chain. The operation is
connected to the Port of Darwin by 88km of sealed roads and is
ideally located for Asian export markets.
In response to the rapid and sharp fall in the lithium price during
the year, the Company took the difficult decision to pause
operations at Finniss to preserve the value of the asset. The
operation now has a small, specialist team overseeing its security,
safety and ensuring the infrastructure remains in a restart ready
condition. We have worked closely with NT regulators to ensure
we continue to comply with all licence operations and maintain
our high environmental standards.
Our restart strategy includes the following:
Retention of skills and experience to ensure a high
standard of site maintenance and operational readiness
A detailed bottom-up assessment of the cost base
A review of the future operating model
Studies into optimisation of the processing strategy
Updated mine scheduling and planning
Resource extension drilling of deposits and targets
within trucking distance of the Finniss processing plant
Any restart decision will be based on the outcomes of the restart
work programs and an assessment of the lithium market conditions,
among other factors. The restart study is expected to be completed
in the first half of calendar year 2025.
7
8
Core Lithium | 2024 Annual Report
Chair’s Letter
Dear fellow shareholders,
I am pleased to present Core’s annual report for the
financial year ending 30 June 2024. This year has been
one of both challenge and resilience, and I want to take
this opportunity to provide a summary of our activities,
focusing on key areas such as safety, mining operations,
environmental compliance, and our strategic response to
changing market conditions.
The lithium industry is small and rapidly
evolving. As a new entrant, Core has had
to navigate the inevitable waves shaping
and shaking all lithium companies. We
demonstrated our resilience by quickly
capitalising on the strong sentiment from
2021 to 2023, successfully financing and
constructing our Finniss lithium operation.
However, when the market sharply turned
from around the start of FY24, just as our
operations were ramping up, we had to
act decisively and take what were tough
decisions to protect your Company.
When the first spodumene concentrate
was produced from the Finniss operation
in February 2023, lithium prices were
nearly US$8,000 per tonne. The
following year, they hit record lows
of US$1,100 per tonne and are
currently trading well below this
level. This meant lithium prices fell by
around 85% throughout our operating
period. This price fall has challenged
the economic viability of most of the
world’s lithium operations.
In response to the deteriorating market
conditions, Core undertook a strategic
review, which resulted in the difficult
decision to stop mining operations
at Grants in January 2024. The run of
mine stockpiles was processed, with
DMS processing stopping in June 2024.
This decision was made with careful
consideration, prioritising the long-term
sustainability of our business and the
interests of stakeholders. The decision to
stop mining has allowed Core to maintain
a strong cash balance while we undertake
exploration and further studies to allow
the Company to recommence mining once
market conditions are favourable.
While the toughest decisions are now
behind us, we are acutely aware of their
impact on our employees and important
stakeholders in the Northern Territory.
The passing of time may have shown
that they were the right decisions in the
circumstances, but this does not diminish
our regret for reducing our workforce
and placing operations on hold to protect
the value of our assets. Our commitment
now is to build a management team that
is dedicated and capable of leveraging the
platform we have created to transform
Core into a much stronger operator
in the future. We are steadfast on this
path, focusing on sustainably rebuilding
shareholder value across our business.
Despite the challenges of FY24, several
positive outcomes were achieved. As a
Board, we are pleased with our safety
and sustainability performance during a
period of volatility. Our commitment to
rigorous safety protocols and continuous
improvement has reinforced a secure
working environment for all employees
and contractors. We have invested in
training and safety systems to maintain
high safety standards across our
operations, safeguarding our workforce
and bolstering our operational efficiency
and industry reputation.
Our ramp-up of operations at Finniss
showed progressive improvement, with
demonstrated plant performance and
recovery improvements achieved over
FY24. We demonstrated the efficiency and
safety of our logistics chain in transporting
products from our operations to our
customers. We also advanced our second
mining front with the box cut commencing
at the BP33 project. Importantly, we ended
FY24 in a solid financial position, with a
cash balance of more than $87 million and
no debt, providing a solid foundation for
our future endeavours.
Core will continue to act ethically and keep
our operations in good standing before
any restart. We remain committed to
working closely with local NT stakeholders
and collaborating with the traditional
landowners of the lands on which we
operate. I’d also like to thank the NT
government, which has remained a
supportive partner. I encourage all
shareholders to review the sustainability
report contained within this document,
which outlines our strategy, key objectives
and achievements during FY24.
This past year, we experienced several
changes in our team as part of our ongoing
efforts to move the business forward. I
want to thank all those who contributed
during this period and acknowledge the
executive team’s leadership, particularly
during the transition phases and
restructuring.
While the strategic plan and the
cessation of mining and processing
were implemented, it was critical that
the Board’s focus turn to securing highly
capable executives to ensure the change
could be sustained and that the Finniss
operations were ready to restart.
Following the departure of CEO Gareth
Manderson in March 2024, CFO Doug
Warden was appointed interim CEO.
Doug did an outstanding job in this
position, and the Board extends its thanks
for his dedication and professionalism
during his time in the role.
In May 2024, the Board was pleased to
announce the appointment of a new
CEO, Paul Brown. Paul’s previous
leadership roles with Hastings Technology
Metals, Mineral Resources Ltd, and
Fortescue Ltd, as well as his extensive
experience in the lithium market
operations, make him the ideal person
to spearhead the restart of studies and
optimise Finniss Operations.
9
With the appointment of Doug Warden
as interim CEO, James Virgo was
promoted to interim CFO in March
and was confirmed as permanent CFO
in May 2024. James is an experienced
finance professional with extensive
financial, commercial and taxation
experience. James is the ideal person
to drive Core’s business development
and capital management activities.
Andrea Hall resigned as a non-executive
director of Core in March 2024. Andrea had
been a director of Core since April 2023.
On behalf of the Board, I thank Andrea
for her significant contribution to Core,
including as Chair of the Risk Committee.
Our company has a solid balance sheet
and a robust financial position, allowing
us to navigate market fluctuations and
seize opportunities when they arise.
We continue to invest in exploration
and development activities, focusing
on expanding our resource base and
identifying new growth opportunities.
Our exploration teams have made
promising discoveries, which we believe
will contribute to Core’s future success.
The lithium industry remains one of the
most exciting and dynamic industries
in which to participate. There remains a
clear prospect for growth in the long term,
but we expect to continue to see volatility
in the short term. While this will be a
challenge, it also presents an opportunity
for Core to be in a position to resume
operations from a lower cost base and
with higher productivity to capitalise on
any future price upswing. We have built a
team and a strategy around this objective
and are committed to delivering on this
plan and, in doing so, providing for Core
shareholders.
Our strategic goals for FY25 are to
streamline business costs, get Finniss
Operation restart ready and continue
near mine and regional exploration.
We are well‑funded to deliver on these
objectives and look forward to sharing
the results of these efforts in FY25.
In conclusion, the past year has been
one of adaptation and resilience for Core.
While market conditions have presented
challenges, our commitment to safety,
operational excellence, and environmental
stewardship remains unwavering. We
have taken proactive steps to navigate the
current landscape and are confident in our
ability to capitalise on future opportunities
as the lithium market recovers.
I want to thank our dedicated employees,
management team, and board of directors
for their hard work and commitment. I also
thank our shareholders for their continued
support and confidence in Core.
Yours faithfully,
Greg English
Non-Executive Chair
Core Lithium Ltd.
We continue to invest
in exploration and
development activities,
focusing on expanding
our resource base and
identifying new growth
opportunities.
10
Core Lithium | 2024 Annual Report
Chief Executive Officer’s Report
Dear shareholders,
It is a pleasure to write to you for the first time
as the Chief Executive Officer of Core, a
position I have held since June 2024. I am
happy to be in this role and believe Core has a
tremendous opportunity to create long term
value for our shareholders and important
stakeholders in the Northern Territory.
We have a highly strategic and valuable
infrastructure at our Finniss Lithium
Project and critical operating experience
from the past two years, which we
continue building within our business.
At the same time, the lithium market
is experiencing significant challenges,
so we will be patient and methodical
in planning to potentially bring Finniss
back online with a lower cost base and
a more sustainable operating future.
We have a well built dense media
separation (DMS) plant, which the Core
team successfully commissioned and
ramped up to the point where it achieved a
monthly lithium recovery rate of 65% before
being placed on care and maintenance
when all stockpiles were processed. This
is a testament to the high quality design of
the facility, and we believe we can further
improve these recoveries with further
optimisation and potential modifications.
For those I have yet to meet, I am a
Mining Engineer with over two decades
of experience spanning lithium, iron ore,
and major bulk commodities. My career
has seen me contribute to developing
and operating world‑class projects,
including ramp‑up and steady-state
management of significant greenfield
operations. In recent years, I’ve focused
extensively on lithium, overseeing
operations and development projects
that have played a key role in advancing
the sector. Leading Core and steering
the future restart of the Finniss Mine is
an exciting new chapter where we stand
on the cusp of delivering significant
value. Core holds ~500km2 of the Bynoe
pegmatite field in the NT, accessible
via sealed roads and other critical
infrastructure. Large sections of the
project area remain underexplored,
and there is exceptional potential for
further lithium deposits within trucking
distance of the Finniss processing plant.
Finniss itself is ideally located 88km
from Darwin and the port. This is a
proven logistics chain we do not share
with other major mining companies.
I have been impressed by the support
from the NT government, local traditional
owners and community groups. We have
worked hard to build solid, long standing
relationships in the Northern Territory,
and we all want the Finniss operation to
succeed. We have shown that we can create
a competent and loyal workforce from
within Darwin and the surrounding regions,
which gives us confidence in our ability to
create a team as our restart plan evolves.
Finniss produces a high quality, coarse
grained spodumene concentrate, which
our long term offtake partners in China
highly regard. We will continue to maintain
these relationships while we go through
the restart study process.
Core has accomplished a lot over such
a relatively short period. Since its initial
discovery in 2016, the Company has
completed extensive drilling, technical
workstream, feasibility studies, project
financing and has brought the operation
online in 2023. The typical timeline from
discovery to production of a new lithium
mine is usually more than 10 years. This
puts us in an enviable position to capitalise
on a recovery in the lithium market
compared to other lithium developers.
After less than a year of operations, the
decision to suspend the Finniss operation
was challenging but ultimately necessary in
light of the rapidly declining lithium market.
While this had a difficult impact on many of
our people, it was crucial in preserving the
long term value of our assets. By making
this decision, we’ve positioned ourselves
for a strong restart, a path where others
may not have had the same opportunity.
We’ve also retained critical technical
knowledge vital to maintaining asset
integrity and ensuring full compliance
with our obligations during this interim
period. Core continues to operate under
a culture of high performance, highly
augmented by the recent appointment
of James Virgo as Chief Financial Officer.
Under his guidance, we will continue
to enhance our lean team with the
relevant expertise ahead of our planned
restart plan.
While Finniss operations are suspended,
our entire focus is on advancing the
Finniss operational restart strategy,
with a detailed bottom-up assessment
of the cost base and future operating
strategy currently underway. Our goal
is to deliver opportunities to improve
operating efficiencies, including process
improvements in the mining schedule and
project pipeline. We anticipate the key
outcomes of this Restart Study to be ready
in the first half of CY25.
11
By making this decision,
we’ve positioned ourselves
for a strong restart, a path
where others may not have
had the same opportunity
A key element of our plans is to build our
resource inventory within trucking distance
of Finniss. We also want to deliver value
for our shareholders by advancing our
earlier stage exploration assets, which have
untested potential for commodities outside
of lithium. By making appropriate, low cost
investments in exploration, we believe we
can build and realise value for shareholders
while keeping our primary focus on the
lithium restart strategy.
I want to thank our shareholders for their
encouragement since I joined the Company
through challenging conditions for both the
lithium sector and equity markets. We have
a strong balance sheet and disciplined
approach to capital spending that will allow
us to see through this part of the cycle
and position the business and our Finniss
operation for the recovery. Finniss is a fully
permitted, proven operation which can
be rapidly restarted for minimal capital
in the right market conditions. With key
workstreams for the restart well
underway, we are looking forward
to a brighter year in FY25.
Yours sincerely,
Paul Brown
Chief Executive Officer
Core Lithium Ltd.
12
Core Lithium | 2024 Annual Report
Operations
Operating and Financial Review
Continued Ramp-up and Operational Pause
The ramp-up of mining and processing at the Finniss Lithium
Operation continued in the first half of FY24 before a strategic
decision in January 2024 was taken to pause the operation in
light of a deteriorating lithium price and market outlook.
Mining
Mine performance at the Grants open pit
continued to improve in the early part of
the financial year, following the successful
implementation of several performance
improvement initiatives. This resulted
in substantial increases in total material
moved as operations continued to ramp
up over 1H FY24.
There was a concerted focus on wet
season preparedness, in response to the
above average rainfall which hindered
operations in FY23. Additional high volume
water storage facilities were constructed,
haul roads were sheeted, and higher
capacity pumping infrastructure was
used for dewatering.
This investment in haul road improvements
and upgraded dewatering infrastructure
significantly reduced the time to return to
normal mining operations during the FY24
wet season. The site experienced above
average rainfall during November 2023,
which was earlier than the previous year.
However, the site team was well prepared
to respond to these conditions.
A second geotechnical monitoring radar
was installed to improve prediction of
wall movement and ensure preventative
measures were established proactively.
However, in response to falling lithium
prices and subdued market fundamentals,
Core completed a strategic review and
elected to suspend all mining operations at
Finniss in January 2024 with processing of
stockpiled ore continuing until June 2024.
Core will now prioritise the
safe preservation of the
Finniss assets in a restart
ready state following the
cessation of mining and
processing activities.
13
Processing
The dense media separation (DMS) plant
with nameplate processing capacity of
1 million tonnes per annum at Finniss
operated throughout the majority of FY24.
As operations continued to ramp up in the
first half of the period, plant performance
continued to improve through an
integrated operational approach.
The Group focussed on increasing
equipment availability and lifting
productivity in the DMS plant which
led to record ore crushing throughput,
processing and a significant improvement
in recoveries. Process improvement works
were conducted during Q4 2023 resulting
in the DMS plant running at higher rates
increasing from 80 tonnes per hour to
90 tonnes per hour during the plant’s
ongoing ramp up phase.
A series of trials were also completed,
including optimised blast parameters in
the pit to produce the desired ore feed
size, adjusting screen size in the crushing
circuit, DMS media reagent dosing set‑point
and timing adjustments, optimising the
ultra‑fines circuit, adjustments to the
roll crusher and commissioning of a
mica classifier.
The initial set of improvement actions and
operating parameters identified by this
work produced substantial improvement
in recoveries from ~47% in the first half
of production in 2023 to 65% towards the
end of the period.
Core produced 95,020 tonnes
of spodumene concentrate
during the reporting period,
exceeding the revised guidance
of 90,000 – 95,000dmt.
Successful discussions were held
with Core’s key offtake customers,
which resulted in the broadening of the
specification of spodumene concentrate
to include acceptance of grades with a
minimum of 4.5% Li2O. Production of
a concentrate at these lower grades
resulted in higher recoveries and
improved lithium yield.
Plant reliability improvements increased
plant runtime and led to more stable
plant conditions. These results, along
with further optimisation of plant density
setpoints achieved an improved final
concentrate grade averaging 4.8% Li2O.
Following suspension of mining, Core
continued the processing of existing
ore stockpiles until all stockpiles were
exhausted. During this time, increasing
equipment availability and lifting
productivity was the primary focus at
the DMS plant, which led to record ore
crushing throughput, processing and
improved recoveries.
Restart assessments remain underway
to facilitate further cost reductions and
improve operational performance when
lithium market conditions improve.
14
Core Lithium | 2024 Annual Report
Operations
Operating and Financial Review
Sales and Marketing
Core has long-term offtake agreements
in place with two leading Chinese
companies, Sichuan Yahua and Ganfeng.
All spodumene concentrate sales for FY24
were completed under these agreements.
In early July 2023, a shipment of
approximately 13,100dmt of spodumene
concentrate was loaded for export to
China. This shipment represented the
balance of the commissioning and first
production tonnes (18,500dmt total) sold
to Sichuan Yahua under the additional
sales agreements previously announced
in March 2023.
In early September 2023, the inaugural
10,000dmt spodumene concentrate
delivery was made into Core’s longterm offtake agreement with Ganfeng.
The Group also sold its first parcel of
15,000dmt of lithium fines with a grade
of 1.3% Li2O with the ship leaving Darwin
Port on 8 September.
Suspension of operations
Throughout the period, significant
decreases in the market price for
spodumene concentrate culminated in
Core’s decision to suspend all ongoing
mining and processing operations.
Discussions commenced with offtake
partners regarding future delivery
schedules and the potential impact of
the decision to suspend mining on the
long‑term offtake agreements.
The final spodumene shipment for FY24 of
10,413dmt left Darwin in mid-June 2024.
As at 30 June 2024, Core has 5,178dmt
of spodumene concentrate available at
Finniss for sale, bulk testing or qualification
by potential customers. The Group is
assessing its options for this material.
Core achieved record sales
of 97,423dmt, exceeding
the FY24 revised guidance
(80,000dmt–90,000dmt) at an
average grade of 4.8%.
Lithium fines
To address lower recoveries from the
DMS plant in the near-term, a strategy of
extracting lithium fines material and selling
it as a ~1% lithia product was adopted. A
total of 66,140wmt of fines were extracted
from the storage facility and transported
to the Darwin port for shipment.
In total, lithium fines sales were
66,140wmt for the period.
As at 30 June 2024, Core has up to
75,000wmt of lithium fines available at
Finniss for sale, bulk testing or qualification
by potential customers.
Restart Strategy
Core is now advancing its restart
strategy, designed to enhance future
operations from a cost, product quality
and sustainability perspective, ensuring
readiness for improved lithium market
conditions.
The Group is now prioritising the safe
preservation of the Finniss assets in a
restart ready state following the cessation
of mining and processing activities. It is
also using the pause of operations to
advance its operational restart strategy,
aiming to strategically capture substantial
value from a restart of operations upon
stabilising market conditions.
The updated operating strategy involves
a detailed bottom-up assessment of
the cost base and the operating model.
Opportunities to improve future operating
efficiency and reduce expenses will be
actively investigated. There will be detailed
analysis and further refinement to the
processing strategy, mining schedule and
project pipeline including the integration of
the BP33 development and other deposits.
The restart strategy aims to
strategically capture substantial
value from a restart of
operations upon stabilising
market conditions.
Integrated with this work is the review
of the long-term sustainability and
regulatory approvals strategy in the
Finniss region. Activities in this space have
been progressing throughout FY24 and
will continue to advance in collaboration
with government, community and other
stakeholders as part of FY25 work
packages.
The restart study is due to be completed
in the second half of FY25 and any restart
decision will be subject to the outcomes of
the study and market conditions, among
other factors.
Key on-site activities for the remainder of
the period included genera